The bathroom tiles are paved, can you still do a closed water test, I see that the wall is not brush

Updated on Bathroom 2024-09-15
3 answers
  1. Anonymous users2024-01-24

    Now have done a good job of testing the water does not leak, but can not guarantee that it will not leak in the future, do a secondary drainage when changing the drainage before laying the bricks, even if the bricks are paved after the leakage is fine, try the drain with a bucket of water poured around the side to see if there is a collection of water, whether the water flows to the floor drain.

  2. Anonymous users2024-01-23

    1. The bathroom floor waterproofing must be done, generally brushing flexible waterproofing agent, this does not need to be covered with waterproof cloth, if you have tried the water, it will generally not leak again, unless you drill holes in the ground.

    2. The closed water test is done before laying the floor tiles, that is, after the waterproofing, not after the tiles are pasted. , so you are now experimenting with vain, after all, your floor drains are installed. There is no need.

    3. Tile grout is done after the tile is pasted, and the grout agent is generally used, but it doesn't matter where some people directly take white lime and sprinkle it on it, and then touch it evenly.

    4. Generally, the tiles are dry-paved, and it is recommended to stand at least 3 days later;

    5. Test the lowest floor drain, just splash water at the farthest place from the floor drain to see if the water flows quickly to the floor drain, if there is no floor drain where a large number of people gather, then it proves that the floor drain is not the lowest.

  3. Anonymous users2024-01-22

    I have a friend who does this,

Related questions
5 answers2024-09-15

The waterproof test is best to close the water test before laying the tiles, in case of any water leakage, it is too late to make up again. Now that the tiles have gone up, then wait for the tiles to dry, scrape the gaps in the bricks, and use the water directly, and at the same time do the water discharge inspection. In case of water leakage, you will have to smash the tiles before installing. >>>More

4 answers2024-09-15

Waterproofing is to be done at the base level, now the surface layer has been completed, can only use the waterproof performance of the good special honey, both the wall and floor tiles of all the gaps carefully filled, fill all the floor drains, sewer pipes and floor tiles of the joints should be used to plug the king carefully is not good, this is only a palliative remedy, in the future or to maintain frequently.

3 answers2024-09-15

Hello, the waterproof layer of the bathroom is to be laid after the completion of the hydropower renovation. >>>More

1 answers2024-09-15

As long as there is no water leakage downstairs, it is normal to evaporate, in fact, most of it is absorbed by the cement wall.

1 answers2024-09-15

Do a closed water test to plug the floor drain with a lime bag, and then take out the lime bag after the test.