The ceiling process of the top surface of the computer room

Updated on Suspended ceilings 2024-08-09
5 answers
  1. Anonymous users2024-01-24

    1) Use bolts to weld the light steel keel to the ceiling, first connect the main keel, and then connect the secondary keel.

    2) Put the middle layer of the rubber plate and the galvanized iron plate on the bottom layer, inlay it into the keel, and some should be connected with screws.

    3) Glue the surrounding wall, and then brush a dustproof paint.

  2. Anonymous users2024-01-23

    What is the construction process?

    Light steel keel - iron plate or aluminum plate - painted.

  3. Anonymous users2024-01-22

    Dear, hello, I will give you your question, I am sorting out the answer, it takes some time to type, please wait a while, thank you!

    In order to ensure that the top of the computer room is waterproof and dustproof, the ceiling of the computer room needs to be sprayed with waterproof paint and dustproof paint for surface treatment. (See the annex for details) materials to prepare cement, fine sand, waterproof coatings, dustproof paints, etc., and enter the site to pass the inspection and have factory certificates and material certificates. 1. Before the top treatment, the site should be cleaned up, and all the building materials and construction waste that hinder the construction of the site should be cleaned up.

    2. Set up the roof construction operation platform shelf. 3. Before the large-scale construction of the top of the computer room, the model should be made, and the large-scale construction should be carried out after the appraisal of the project supervision unit. Construction process 1, process flow:

    Cleaning, repairing, filling and installing embedded parts, top leveling, waterproof coating, dustproof paint, and concealment engineering acceptance. 2. Cleaning: Remove and shovel all the concrete burrs and steel bars left on the top, and use a brush to carry out basic cleaning to remove dust.

  4. Anonymous users2024-01-21

    1. Dustproof paint. 2 booms. 3. Rubber and plastic panels are glued between the booms. 4 distribution keel, 5 installation of microplate, 6 (punched aluminum plate), if, your computer room requirements are high, to use not less than 5 mm thick iron plate, is the first step of welding, requiring all the weld gaps, tight can not leak Han,

  5. Anonymous users2024-01-20

    I don't know what galvanized iron plate is used for, dustproof paint --- light steel keel (according to the spacing of aluminum gusset plates) - rubber and plastic plates --- perforated aluminum plates are pasted between the keels.

Related questions
2 answers2024-08-09

In principle, it can't be added, the computer room and the office are not a concept, of course, it doesn't matter if you encounter the leader of the brain pumping, how to add it, as long as you don't destroy the original ceiling, wall, floor, it doesn't matter if you destroy it, all the leaders in Dahua have the final say. . .

1 answers2024-08-09

If the temperature of the space above the roof is not much different from the temperature in the computer room, it is not necessary to do insulation. >>>More

4 answers2024-08-09

In only LED lights are installed, no other electrical appliances are installed! TO ACHIEVE 10CM UNDER THE ROOF! USE A WOODEN STRIP AS THE MAIN KEEL 5CM CAN BE...

3 answers2024-08-09

This is a sprinkler head that dismantles the original sprinkler head and changes the pipe to a sprinkler head that sprays the ceiling.

3 answers2024-08-09

Perforated aluminum gusset plate, back pasted with sound-absorbing paper, with 15 25mm thick glass sound-absorbing cotton, aperture, thickness, specification 600*600. Because of the size of this size of the board, the price is moderate, fireproof, sound and heat insulation, light weight, very suitable for the computer room.