Bathroom PVC ceiling step operation

Updated on Suspended ceilings 2024-08-15
1 answers
  1. Anonymous users2024-01-24

    1. Clarify the location.

    Before installation, the location should be determined, the height of the ceiling installation will affect the sensory experience of the whole room, it is not easy to be too low, and the ceiling that is too low will make the space appear oppressive. After determining the height, use the ink line to bounce the elevation on the surrounding walls, and the baseline should be clearly marked.

    2. Determine the size of the PVC gusset.

    According to the design of your own ceiling and the total area of the ceiling, you can choose the size and specification of PVC gusset.

    3. Determine the position of the keel line.

    In the case that the size and specification of the PVC gusset have been determined, the next step is to determine the position of the keel line. Because the keel line mainly plays the role of supporting the shape of the external decorative material and fixing the structure, in order to ensure the integrity of the installation, the size and position line of the keel line are determined according to the specifications of the panel that has been determined, and the determined size is marked.

    4. Installation of the main keel.

    Once the location is determined, the installation of the main keel can be carried out. When the main keel is installed, it should be noted that the middle part should be arched, and the height of the keel arch is not less than one of the two hundredth of the span of the room surface, and the position and height of the main keel should be corrected in time after installation, so as to prevent errors. Pull out the elevation control line from the transverse, start from one end and adjust while installing, and then adjust some individual keels with curved warped edges when the large surface is flattened.

    Note that the outlet of the lighting line should be left when the main keel is installed.

    5. Boom installation.

    The installation of the boom is also very important, and there are three requirements for the installation of the boom: the boom should be straight and have sufficient bearing capacity; The boom must be treated with anti-rust treatment; The boom shall not exceed 300mm from the end of the main keel, if it is exceeded, the boom must be added, and the lap weld needs to be firmly welded to avoid the keel falling.

Related questions
2 answers2024-08-15

What else can I do if it's already like this, just use it like this.

2 answers2024-08-15

Please hourly workers are the most convenient, and they often wipe the ceiling or range hood, etc., very experienced, whether it is the scrubbing method or the choice of limb cleaning teasing detergent is much stronger than you, find a housekeeping company to contact, the price will not be very expensive, save time and effort.

2 answers2024-08-15

Kitchen and toilet ceilings are to integrate ceilings!

1 answers2024-08-15

Generally, meters to meters, according to the actual situation. >>>More