The bathroom was waterproofed and not dried for a week

Updated on Bathroom 2024-08-20
4 answers
  1. Anonymous users2024-01-24

    After the waterproofing of the restroom is completed, you must wait for the coating of the waterproofing paint you have chosen"Finalization"

    That is: the meaning of complete solidification.

    The water can only be tested after the final setting.

    All kinds of waterproof coatings are clearly stipulated in the implementation standards of the product.

    The requirements for the final setting time vary from product to product.

    However, in general, such as the commonly used "general-purpose K11 waterproof slurry", the water can be tested 24 hours after normal construction.

    The test time is 24 to 48 hours.

  2. Anonymous users2024-01-23

    It dries quickly, and it can be dried in a day.

  3. Anonymous users2024-01-22

    What type of waterproofing is used? You can test the water in 24 hours.

  4. Anonymous users2024-01-21

    The common reasons why the waterproof layer does not condense are as follows:

    1.If you do not mix according to the requirements of the manual, you may add water without authorization or add too much water;

    2.The weather is humid or the waterproof parts are not well ventilated, resulting in the waterproof layer is not easy to condense and dry;

    3.The waterproof material is expired or the quality itself is defective, resulting in a situation that is not easy to condense.

Related questions
5 answers2024-08-20

1. Inspect and accept the appearance, variety, specification, packaging, size and quantity of materials, and form corresponding acceptance records. >>>More

3 answers2024-08-20

Put the vinegar on a dish, or the orange peel to dry and hang in the bathroom, light it at intervals, and then replace it with a new dried orange peel and continue to operate as before.

5 answers2024-08-20

After the bathroom is waterproofed, you can do the closed water test after the waterproof layer is completely dry, the closed water test time is generally 48-72 hours, and the closed water test is completed after the ground is dry, and you can use it normally after two days after the brick. >>>More