In the decoration of the kitchen and bathroom at home, whether to hang the ceiling or wrap the pilla

Updated on Suspended ceilings 2024-07-31
3 answers
  1. Anonymous users2024-01-24

    It depends on what form you use to wrap this column, if it is a cabinet, you have to wait until the ceiling is installed after the cabinet is wrapped, if you use the form of red brick masonry or wood with waterproof gypsum board to stick bricks, you have to get it first, if it is a second-hand house, I recommend using cabinet wrapping or using the material of the ceiling to do.

  2. Anonymous users2024-01-23

    First wrap the water pipe columns, paint, til, and the ceiling is done last.

  3. Anonymous users2024-01-22

    It depends on what kind of burial form you use to wrap this column, and if it is a cabinet, you have to wait until the ceiling is installed.

    Cabinet lead ants to wrap, if the use of red brick masonry form or wood with waterproof gypsum board to stick bricks, you have to get it first, if it is a second-hand house.

    I recommend wrapping it in cabinets or using the material of a bright-back ceiling.

Related questions
1 answers2024-07-31

Hello, it is recommended to finish painting the wall before going to the suspended ceiling! Water heater you need according to the height of the roof; The height of the water heater installed is also determined by your aesthetic needs! If you want to wrap the water heater into the ceiling, then you can use the water heater in Qin Wu'an, if you don't need the suspect or you can hang the ceiling first!

8 answers2024-07-31

Ceiling first or brick first.

Generally speaking, it is to paste the brick first and then the ceiling, and by the way, I will give you a science popularization of the overall decoration order of the bathroom. >>>More

1 answers2024-07-31

Depending on what project progress you have reached now, for example, your bathroom door has been installed, and the living room and kitchen and bathroom can be carried out together, if the kitchen and bathroom door is not installed, you can only do the living room, because the door is not installed and your ceiling is not sure how to hang.

1 answers2024-07-31

Generally, the hydropower should be done first, and the light line on the ceiling should be done first.

1 answers2024-07-31

The general process of decoration is: water and electricity transformation, bricklayer, carpentry, paint should be the ceiling first and then paste the wallpaper bedroom cabinet if it is a finished product, wait for the floor to be paved and then enter the furniture If it is furniture made on site, you can first make a cabinet, and then lay the floor, so as to save the floor under the cabinet, the general practice is to hit the cabinet first and then lay the floor.