Is the name of the secondary structure masonry wall kitchen to be built separately?

Updated on Kitchen 2024-09-15
1 answers
  1. Anonymous users2024-01-24

    Since the construction of the secondary structure wall has been carried out, each building number should pay attention to the following part of the wall can only be masonry after the installation of the water and electricity pipelines is completed; Otherwise, the masonry finished wall still needs to be removed.

    Secondary structure refers to some non-load-bearing masonry, structural columns, lintels and other parts that need to be completed before decoration in frames, shear walls and frame shear projects, which are called secondary structures.

    The process time of the secondary structure is constructed after the completion of the construction of the primary structure (referring to the load-bearing member part of the main structure), which is relative to the load-bearing structure, and is a non-load-bearing structure, and the maintenance structure, such as structural columns, ring beams, water-stopping anti-beams, parapet walls, roof-pressing walls, infill walls, partition walls, etc.

    Masonry engineering refers to the masonry of ordinary clay bricks, load-bearing clay hollow bricks, autoclaved lime sand bricks, fly ash bricks, various small and medium-sized blocks and stones. At present, China is carrying out wall reform, in order to save farmland to use, less use of ordinary clay bricks, and further promote the application of various hollow blocks.

    According to the "Unified Standard for Acceptance of Construction Quality of Construction Projects", GB50300

    1. The main structure division project includes: concrete structure, steel (pipe) concrete structure, masonry structure, steel structure, wood structure, grid and cable membrane structure and other 6 sub-division projects.

    Among them, the beams, columns and slabs of reinforced concrete belong to the sub-division of concrete structures, while the masonry works and secondary structural components (structural columns, ring beams, etc.) belong to masonry structures.

    2. The acceptance conditions of the main structure division project are:

    1) The quality of the sub-projects contained in the sub-division (sub-division) project shall be accepted;

    2) Quality control data should be complete;

    3) The inspection and sampling test results related to safety and function of the main structure division project shall comply with the relevant regulations;

    4) The acceptance of the perceived quality should meet the requirements.

Related questions
1 answers2024-09-15

As long as it is within the quality assurance of the house, it will not cause harm, and it can be used through general maintenance. You can report to the property for repair, and the property will deal with it according to the situation.

2 answers2024-09-15

Further lofting on the original baseline to obtain the baseline to be used for the secondary structure, but in doing so, there will be a bad deviation from the primary structure, because when the primary structure is done, there will be an error, if it is large, the secondary structure will go up, and the deviation will come out, and it will not be close, and it is not equal to the imagination. >>>More

1 answers2024-09-15

Let's negotiate, after all, they are all neighbors, how good it is to be polite, let him find someone to help you get it right, if others don't want to, and the money is not much, find someone to get it yourself, there is no need to make a big deal about a little thing. To be harmonious, of course, if you do want people to compensate, you can go to the court to sue if you can't negotiate (usually civil mediation).

1 answers2024-09-15

There must be information to participate in the assessment, and the inspection batch can be divided by layer (no deformation joint) or segmented axis.

1 answers2024-09-15

The openings of doors and windows are not larger than 2000mm, so they can be omitted.