I have two bathrooms to install hot and cold water pipes, as well as sewer pipes, and the bathrooms

Updated on Bathroom 2024-09-11
1 answers
  1. Anonymous users2024-01-24

    One water supply pipe, two drains, one on each faucet floor, two hoses, and one floor drain.

Related questions
6 answers2024-09-11

After designing the drawings of the pipe laying and confirming that the requirements are met, you can start laying the pipeline. The first step must be to find the main valve of the hot and cold water pipes and turn them off, and connect the inlets of the hot and cold pipes to a main valve, so as to facilitate the overall management. >>>More

1 answers2024-09-11

Generally, the hot and cold water pipes in the bathroom are basically at a distance from the ground meters, this height is generally suitable for the washing machine and the mop bucket to receive water, if the home is ready to use the kind of automatic washing machine, it is best to keep it above the meter, the water pipe faucet can be installed when it is high, and other hoses can be installed to connect the water, and it is impossible to connect it if it is low.

3 answers2024-09-11

The height of the bathroom basin and kitchen basin is 45 cm high from the ground. If the bathroom sewer pipe enters the wall, the height is 35-40 cm high. The distance between the hot and cold water pipe joints is only 14-15 cm for the shower mixture, and the rest of the distance can be installed and operated as long as it is good.

1 answers2024-09-11

1.The height of the bathroom basin and kitchen basin is 45 cm high from the ground. If the bathroom sewer pipe enters the wall, the height is 35-40 cm high. >>>More

8 answers2024-09-11

Generally, the hot water is on the left, the cold water is on the right, and you can see the faucet yourself, which has a hot and cold logo on it.