Bathroom waterproofing is tested by that side

Updated on Bathroom 2024-08-20
1 answers
  1. Anonymous users2024-01-24

    After the construction party does a good job, the construction party will do a 48 72-hour closed water test, and the owner will do a good job of testing together.

    Closed water test steps:

    1. After the waterproof construction is completed, the closed water test can be done after the waterproof layer is completely dry (about 24 hours);

    2. Temporarily block the floor drain and the perimeter of the pipeline mouth;

    3. Build a 20 cm high retaining wall at the door;

    4. Start to store water, with a depth of 5-20 cm, and mark the water level;

    5. Water storage time 48 72 hours;

    6. After the water is closed on the first day, see if the water level has dropped significantly, if so, please check whether there is leakage around the roof and pipes downstairs in time, if not, continue to close the water;

    7. On the third day, the water is closed, and the downstairs ceiling and roof pipes are fully inspected.

    8. Carry out the next process after being fully qualified.

Related questions
3 answers2024-08-20

There is no strict requirement for the height of the water test, cover the mouth of the sewer pipe, and it is almost two centimeters above the ground. Keep it for 24 hours, and see that the top surface of the downstairs is not leaky. ,

1 answers2024-08-20

This even if it is a master does not dare to pack a ticket, how good is the waterproofing, with daily use, external factors, etc., especially with the aging of materials over time, there will be leakage gradually, and testing the water for ten days is just a test.

3 answers2024-08-20

Wait until the waterproof layer is all dry, generally 24 hours, depending on the temperature at that time!

1 answers2024-08-20

Capillary phenomenon, it should be that the waterproof layer is too absorbent, and its impermeability should not be good, whether the material is wrong or there is a problem with the construction.

2 answers2024-08-20

The water test to detect whether the waterproof construction of the bathroom and kitchen is qualified is called the closed water test. >>>More