Which comes first, the ceiling of the living room and the tiles of the kitchen and bathroom

Updated on Living room 2024-08-18
5 answers
  1. Anonymous users2024-01-24

    In general, the ceiling is suspended first, and then the floor tiles are laid. The ceiling is carpentry work, and the garbage and dust are very large, even if the bricks are paved and protected with adhesive tape, it is not ideal, and it is difficult to take care of; However, if it is a suspended ceiling (including gypsum board) such as a kitchen or bathroom, it must be pasted with wall tiles and then suspended ceiling, otherwise the joint will definitely not work well (the general decoration team will not care about this detail). Whoever tells you to lay bricks first is an idiot!

    The normal process is also the first carpentry field. I just finished renovating, and I spent money to buy experience.

  2. Anonymous users2024-01-23

    The kitchen is first tiled, and then the ceiling is generally PVC, and the height should be calculated in advance.

    Secondly, it is very bad to use a wooden floor in the living room, at least I don't like to mop the floor on my stomach. Oh, but it hurts to hang the ceiling all the way down.

  3. Anonymous users2024-01-22

    Yes, as long as it does not affect future construction.

  4. Anonymous users2024-01-21

    Most of them do carpentry first and then plasterers.

  5. Anonymous users2024-01-20

    Yes, it doesn't matter.

Related questions
2 answers2024-08-18

Generally, the bricks of the kitchen and bathroom should be lower than that of the living room, because the kitchen and bathroom have water1

1 answers2024-08-18

Depending on what project progress you have reached now, for example, your bathroom door has been installed, and the living room and kitchen and bathroom can be carried out together, if the kitchen and bathroom door is not installed, you can only do the living room, because the door is not installed and your ceiling is not sure how to hang.

1 answers2024-08-18

There is no absolute order of this, the normal construction sequence is that tiling is the first step, then the ceiling, then the cabinet, like this. But in order to save some money for the ceiling, it can also be changed to make the cabinet first, then the ceiling, and the ceiling follows the cabinet. The first step of tiling is constant. >>>More

1 answers2024-08-18

The ceiling is suspended first, then the tiles are pasted, and finally the floor is laid. In this way, the floor will not be walked by too many people, and the floor will not be damaged.

2 answers2024-08-18

Paint the walls! In fact, there is no conflict, as long as you don't brush the kitchen and bathroom, now it is generally tiled, and you can make a kitchen and bathroom ceiling after pasting the tiles.