What are the construction steps of solid wood flooring

Updated on Solid wood 2024-07-14
3 answers
  1. Anonymous users2024-01-24

    Step 1: Grassroots treatment.

    The base layer is uneven, and the wooden floor should be paved after the cement mortar is leveled. The base layer should be no sand, no skin, no ash, no hollowing, no oil stains, and no roughness to the touch. Generally, the floor of the blank room only needs to be cleaned with a broom, and the dust and debris on the floor can be cleaned.

    The second step of solid wood floor construction: install the wooden keel.

    The embedded parts should be made on the ground first, in order to fix the wooden keel, the embedded parts are bolts and lead wires, and the spacing of the embedded parts is 800 mm, and the hole is drilled from the ground.

    The third step of solid wood floor construction: pad the insulation layer.

    Building construction. The base layer and the back of the insulation layer are glued at the same time, and the adhesive surface can be paved when it is not sticky.

    The fourth step of solid wood floor construction: leveling the floor after installation.

    The construction of solid wood floor is to first lay the lining board, on the wooden keel that has been adjusted, use the floor nail full of nails to nail the lining floor nails for more than two times the thickness of the lining board, and leave a 2mm gap between the adjacent lining boards. Then, the one against the wall should leave the 10mm gap of the wall, and then row it up one by one, and nail it obliquely from the concave corner of the floor with floor nails, the nail cap should be smashed flat, the tongue and groove board should be nailed firmly and tightened, and the back of the wooden floor should be brushed with high-quality wood glue.

  2. Anonymous users2024-01-23

    The price of solid wood flooring itself is high, and if the paving area is relatively large, it is also a large expense. How to make this money more worthwhile, in addition to shopping around when purchasing, you also need to be careful and cautious when installing solid wood flooring. Today's floor decoration class will explain the steps of the three solid wood floor installation methods for you in detail, hoping to help the owners who are decorating.

    Solid wood floor installation method of direct installation].

    Required installation materials: moisture-proof cloth + flooring.

    Ground requirements: The difference between height and height is plus or minus 2mm

    Suitable for: non-geothermal and geothermal.

    Installation steps: 1. Tidy up the floor first, and a smooth and clean base layer can lay a solid foundation for future use. Then lay a moisture-proof cloth on the ground, the moisture-proof cloth should cover the entire ground, in order to achieve the balance effect of moisture-proof and sound insulation, the choice of geothermal cushion material must not be too thick, you can use heat conduction.

    2. Install the solid wood floor above the moisture-proof cloth.

    Solid wood floor installation method of elevated installation].

    Required installation materials: special keel + thick splint + moisture-proof cloth + floor.

    Ground requirements: the flatness does not exceed 5mm or the ground above the second floor.

    Suitable for: Non-geothermal.

    Installation steps: 1. Prepare a special wooden keel, pay attention to the spacing between the wooden keels should be less than or equal to 350mm, and the frame surface of the keel should be kept flat.

    2. Coat the top of the wooden keel with water-resistant adhesive, and then lay the splint with a thickness of about 12mm on the keel that was erected before, the specification of the splint sawing should not be greater than 600 * 600mm, and the spacing between the splint and the splint is 5 10 mm, and then use the air gun to nail the headless nail into the splint and the skeleton.

    3. Lay a moisture-proof cloth on the top of the plywood, and then install the wooden floor on the moisture-proof cloth, and nail it into the fixed floor at a 45-degree angle of the head nail on the male tenon.

    Solid wood floor installation method of suspension type].

    Required installation materials: moisture-proof cloth + flooring.

    Ground requirements: the height difference is plus or minus 2mm

    Suitable for: Non-geothermal.

    Installation steps: 1. Trim the ground first, and a clean and solid ground base is what is needed to lay the floor.

    2. Usually the mat is laid on the ground, and then the floor glue is used on the top of the mat to assemble them into one.

    Conclusion: Although all the projects of home decoration are completed by professionals, we can better supervise the project and make our own floor paving more beautiful.

  3. Anonymous users2024-01-22

    1. The pavement scheme should be constant.

    For each stadium, or theater stage, what materials to pave, and how to pave, are determined according to the actual parameters of the sports venue and the investment budget. Therefore, once the sports wood floor paving scheme is decided, it should not be changed easily.

    Frequent changes to the design and construction plan of sports wood flooring will cause additional investment and even affect the construction period. Therefore, in the design of sports wood floor paving scheme, it is necessary to communicate and coordinate with sports wood floor manufacturers, clarify standards, and avoid unnecessary problems.

    2. Customized products should be in advance.

    The overall structure of the sports wood floor is basically all solid wood structure, and the moisture content of the floor will be done according to the climatic conditions and moisture content changes of the installation project site during production, which is generally about 6%-14% on average. Before ordering sports wood flooring, it is important to allow sufficient time for production in order to ensure the quality of the flooring.

    3. Avoid cross construction.

    Cross construction, that is, the paving of sports wood floors, is carried out at the same time as other construction projects of stadiums and conflicts with each other. The sports wood floor paving project should avoid cross construction, so as to affect the smooth progress of the sports wood floor pavement, or the construction of other stadium construction projects destroys the paved sports wood floor floor.

    4. Supervision and acceptance should be involved.

    Although it is said that the installation project of sports wood flooring is operated by the pavement engineer of the sports wood floor manufacturer. However, the stadium contractor and Party A should also arrange a special person to be responsible for tracking and supervision, and solve the problems in the installation of sports wood flooring in a timely manner.

Related questions
2 answers2024-07-14

The European-style cement vase column balcony railing is generally made of two-layer foundation wall tiles, paved with a prefabricated foundation plate with a mold, the corridor column is aligned with the foundation hole position, and the top is covered with a strip plate, which is simply like this.

1 answers2024-07-14

1. Acceptance of hydropower buried trunking, acceptance of whether there are cracks on the wall and ground, hollowing, falling off, water seepage on the external wall, etc., if you are a commercial rough house. >>>More

1 answers2024-07-14

Kitchen renovation waterproofing works.

1. Before the kitchen is renovated, it is necessary to carefully check whether there is leakage in the kitchen on the upper floor, and if there is, the waterproof project upstairs should be done before decoration. >>>More

1 answers2024-07-14

According to the measured size, screw into the expansion tube screw in the brick hole on the ceiling, pay attention to the sandwich height between the ceiling and the roof is not less than 25cm, the screw must be perpendicular to the ceiling, and fixed firmly, and keep parallel between the 6 screws. Subtract 5mm from the length of the installation and then cut off the required triceratops. After the triangular hanger is sleeved into the triangular keel, the triangular hanger is stuck on the main keel. >>>More

3 answers2024-07-14

First, the construction conditions of basketball wood flooring. >>>More