The bathroom tiles of the simple room have been paved, how to see the waterproof effect

Updated on Bathroom 2024-04-29
3 answers
  1. Anonymous users2024-01-23

    Under normal circumstances, the standard practice is to wait until the waterproof layer is completely dry, and then start to do the closed water test, and wait until the closed water test is passed before attaching the tiles.

    Now that the tile has been pasted, then because the tile itself contains a certain water absorption, so it is necessary to appropriately extend the time of closed water, the following is still a detailed operation method:

    1. After the waterproof construction is completed, the closed water test can be done after 24 hours;

    2. Temporarily block the floor drain and the perimeter of the pipeline mouth;

    3. Build a 20CM high retaining wall at the door;

    4. Start to store water, with a depth of 5-20 cm, and mark the water level;

    5. Water storage time 48 72 hours;

    6. After the water is closed on the first day, see if the water level has dropped significantly, if so, please check whether there is leakage around the roof and pipes downstairs in time, if not, continue to close the water;

    7. On the third day, the water is closed, and the downstairs ceiling and roof pipes are fully inspected.

    8. Carry out the next process after being fully qualified.

  2. Anonymous users2024-01-22

    In the closed water test, the water level is a few centimeters higher than the highest point of the floor tiles, and after two or three days, check whether there is water seepage downstairs.

  3. Anonymous users2024-01-21

    The closed water test, basically according to the experience of the workers, is generally waterproof very well.

Related questions
3 answers2024-04-29

It is okay not to lay tiles, but after waterproofing, it is necessary to cement cover treatment - to protect the waterproof layer and increase the aesthetics.

3 answers2024-04-29

Do waterproofing needs to be done on the surface of the water, dig excellent permeability crystalline waterproofing, you can do it yourself on the cement surface with a super permeable waterproof guard (if there are cracks and potholes on the cement surface, fill the complete with metin porcelain glue and then do waterproofing). >>>More

3 answers2024-04-29

There is no way. Only the floor tiles were stripped and redone for waterproofing.

5 answers2024-04-29

If the whole bathroom is not waterproof before the paving, it is recommended to disassemble and redo it is safer, because once the leakage is leaked downstairs or the partition wall of your own house will be more troublesome, if you just want to do another layer on the tile, there is that kind of film-forming water can be brushed on it, which can block the gaps of the tiles and achieve the waterproof effect, but this is not very long.

1 answers2024-04-29

Waterproofing should be done at the base level, and now the surface layer has been completed and can only be treated as follows: >>>More