How to install a plastic gusset ceiling? Find the steps

Updated on Suspended ceilings 2024-01-27
1 answers
  1. Anonymous users2024-01-23

    How to install a plastic gusset ceiling? Plastic gusset ceiling construction technology:

    According to the design elevation of the ceiling, the line should be played on the surrounding wall, and the line should be clear, the position should be accurate, and its level should be allowed to deviate by 5mm.

    Fix the angle aluminum along the elevation line, the role of angle aluminum is the sealing of the edge of the ceiling, the common specification of angle aluminum is 25*25mm, its color should be the same as the aluminum alloy panel, and the angle aluminum is mostly fixed on the wall column with cement nails.

    In order to ensure the integrity of the ceiling veneer and the reliability of installation, it is necessary to arrange the structural size of the ceiling skeleton according to the size and specifications of the aluminum gusset and the area size of the ceiling. Jiuzheng building materials network believes that the basic arrangement of the aluminum gusset veneer is: the plate combination should be complete, when the edge is left around, the edge should be symmetrical and even, and the arranged keel position line is drawn on the top of the elevation line.

    The spacing of the main keel hanging point is selected according to the design recommended series, and the middle part should be arched, and the height of the keel arch is not less than 1 200 of the room surface span. After the installation of the main keel, the position and height should be corrected in time. To control the flattening of the keel, first of all, you should pull out the longitudinal and horizontal elevation control line, start from one end, and adjust the suspension height of the boom while installing.

    After the large surface is flattened, adjust some single keels with curved warped edges until the smoothing meets the requirements.

    The boom should be straight and have sufficient load-bearing capacity. Jiuzheng building materials network believes that when the boom needs to be lengthened, it must be lap welded firmly, and the weld is uniform and full. For anti-rust treatment, the boom shall not exceed 300mm from the end of the main keel, otherwise the boom should be added to avoid the main keel falling, and the secondary keel (the same as the middle keel or small keel) should be installed close to the main keel.

    Comprehensively correct the position and levelness of the primary and secondary keels. The connectors should be installed in dislocation, and the installed ceiling skeleton should be firm and reliable, and the next step of construction can only be carried out after meeting the relevant specifications.

    When installing the square aluminum gusset, the secondary bone should be straightened. The gusset plate should be flat and not warped, and the flat error of the ceiling plane should not exceed 5mm.

Related questions
9 answers2024-01-27

How to dismantle the plastic gusset ceiling Hello dear, to remove the plastic gusset, first remove the wooden strip at one end of the gusset, and then take out the gusset one by one from the wooden strip of the trembling pat. When removing the plastic gusset, special attention should be paid to the safety of other equipment and facilities in the ceiling. For the gusset of the kitchen and the bathroom room, the ventilation duct and flue should be avoided when dismantling, and the circuit pipe in the ceiling should not be removed by yourself.

1 answers2024-01-27

Install an adapter box first, which is on the TB.

It is recommended to install LED integrated lamps to save energy. >>>More

4 answers2024-01-27

According to the size of the lamp go to the power tool store to buy a hole opener, install it on the pistol drill, if the opening is less, use a wooden square, smash two nails on it, pay attention, the distance between the two nails is the radius of the light hole, and then draw a circle on the gusset like a compass, pay attention, the position of the light hole try to avoid the keel or wooden square. Hope it helps!

2 answers2024-01-27

Just use an electric hammer to hit the hole, fix the hanging ribs with plastic expansion, and fix the gusset plate with the keel matching the chandelier.

6 answers2024-01-27

Elevation of elastic line Install the main keel 62616964757a686964616fe78988e69d8331333365653236 Install the boom Install the side keel Install the plastic gusset Install the site. Draw a line along the perimeter of the wall, punch the wooden needle under the electric hammer (including the wooden keel and the wooden needle fixed with the yin angle line), fix the keel around it, and nail the keel in the middle according to the width of the gusset to ensure that the gusset socket is well fixed with the keel. The four corners are also fixed. >>>More