How long after the bathroom tile is pasted can you install the toilet, the hole in the wall has been

Updated on Bathroom 2024-10-02
7 answers
  1. Anonymous users2024-01-24

    If it is pasted with cement mortar, then you can punch holes when the cement mortar is dry and hard. Generally, it is 48 hours, in order to ensure the quality, it is recommended to wait a little longer.

    If it's tiled adhesive, it's faster. A day or so is enough.

    To be sure, it is recommended that you ask the tile builders in your home.

  2. Anonymous users2024-01-23

    It is recommended that you install the whole ceiling after the painting, these are installed first if other decoration workers will use, after all, this is a more private thing, it is best to recommend the last installation, because this is not in conflict with others, some bathroom sales stores have free installation services. Hope to adopt.

  3. Anonymous users2024-01-22

    I suggest that you wait for your head to move in and install these, on the line, I am dry water and electricity, the cement is 48 hours before it begins to condense, if you punch holes, it is easy to shine into tiles and fall off, don't worry, wait for the oilman to finish, just install those things very quickly.

  4. Anonymous users2024-01-21

    Generally, the tile can be installed on the third day, however, between the installation to remind the trainees, than the towel rack and other installation holes, do not miss, otherwise it is easy to enter the water, if the hole is really missed, remember to seal it with plastic glue.

  5. Anonymous users2024-01-20

    Wait until the cement inside the tiles has dried before installing the shelves and the like.

  6. Anonymous users2024-01-19

    It is recommended to do it after a week and wait until it has dried to avoid the effects.

  7. Anonymous users2024-01-18

    After 48 hours there was no problem.

Related questions
2 answers2024-10-02

When the tiled cement is dry (usually about 10 days), you can put the washing machine.

4 answers2024-10-02

In general, caulking can be carried out 24 hours after the tile is paved, and it is recommended to walk and step on it until 48-72 hours after the caulking is completed. >>>More

1 answers2024-10-02

I can do waterproofing! The next time you do waterproofing, you can directly pry open the tiles and discharge the stagnant water from the caisson to do waterproofing again! Hope it helps!

1 answers2024-10-02

Toilet construction process.

First the wall tiles, then the floor tiles, then the ceiling, and then the installation of bathroom products. >>>More

12 answers2024-10-02

Home decoration has plastered or attacked the waterproof wall paste. >>>More