Is it too late to do a closed water test when the bathroom floor tiles are pasted?

Updated on Bathroom 2024-08-02
3 answers
  1. Anonymous users2024-01-24

    The bricks can also be waterproof tested, and it does not affect, just like a lot of water in the bathroom when you take a bath, and the water is not a problem even between the floor tiles and the waterproof layer, and it will not cause any impact. The function of waterproofing is only to prevent water from seeping out and causing problems downstairs or other walls, and the bathroom is originally a wet area.

  2. Anonymous users2024-01-23

    Don't do it, it will be more troublesome in case of water leakage. It may be better to do water-based waterproofing on top of the floor tiles twice first.

  3. Anonymous users2024-01-22

    Originally, for insurance, after pasting the floor tiles, it was necessary to do a closed water test again, because beware of the tiles in the tiling, improper construction will damage the original waterproof coating film, causing hidden dangers. Therefore, after pasting the floor tiles, you have to do another closed water test for insurance.

Related questions
1 answers2024-08-02

Just find some fine sand or dirt to use outside – just clean up after the closed water test!

22 answers2024-08-02

The bathroom must do a closed water test, because it is easy to cause water leakage if the waterproof is not done well. If you live downstairs, you will be unlucky. The closed water test should generally be done after doing a good job of waterproofing, and now the floor tiles are pasted and then done, if the water leaks, the floor tiles can only be dug up. >>>More

4 answers2024-08-02

The main purpose of the closed water test is to check whether there is any leakage in the waterproof construction and whether the waterproof function is normal, so it is recommended to do the closed water test after the waterproof layer is completely dry, because if there is a problem with the waterproofing at this time, it can be rectified in time, and the manpower and material resources spent will be relatively small. >>>More

7 answers2024-08-02

After the bathroom is waterproofed, it needs to be thoroughly dried, so that it can do the closed water test, you can contact the residents downstairs in advance, so that the leakage can be informed in time to avoid unnecessary losses of the downstairs residents When doing the closed water test, the depth of water storage can not be less than 20 cm, and the time can not be less than 72 hours, and the water level does not fall is qualified.

3 answers2024-08-02

After 24 hours of waterproofing, the water will be closed, and the water level at the highest point of the plane shall not be less than 2 cm. The entrance is built with a waterproof edge. Acceptance after 24-48 hours of water closure.