If the bathroom is not waterproofed first, is it okay to do the waterproofing after the squatting to

Updated on Bathroom 2024-08-28
17 answers
  1. Anonymous users2024-01-24

    If the bathroom is not waterproofed first, is it okay to do the waterproofing after the squatting toilet is raised up the steps?

    Dear, hello, I'm glad to answer for you that if the bathroom is not waterproofed first, can the squatting toilet be waterproofed after the steps are raised? Answer: If you want to use bricks to build steps in the bathroom, you must wait for the bricks to be built before doing waterproofing, otherwise, waterproofing is done in vain. After the platform defense is built, the waterproofing of the sewage pipe mouth and the contact between the brick and the ground is done together, and then the squatting toilet is installed

    The problem of the bathroom is not so troublesome, and it is okay to do waterproofing after squatting and lifting the steps.

  2. Anonymous users2024-01-23

    It is necessary to make waterproofing first, and then make a squatting toilet.

    The first thing many people do after getting a house is to decorate the work, when doing bathroom decoration, should they do waterproof or squatting toilet first? If the squatting pit is done, is it okay to do waterproofing again? I think we must do waterproofing first, because the squatting toilet in the later stage belongs to the sanitary ware, and the sanitary ware is installed later.

    And when you get the house, you should find that the developer has done a good job of waterproofing the bathroom in advance.

    Because the waterproofing work of the bathroom is particularly important, whether it is the ground or the wall, as long as there is a water source in the later stage, a waterproof layer needs to be made. Once the waterproof layer is not in place, it is easy to have water seepage, and even affect the residents downstairs. Therefore, when you do bathroom waterproofing work, you must do waterproofing first, and then install a squatting toilet.

    When doing waterproof work, we must clean all the bathroom floors, without any convex or concave places, or even cracks, so that the waterproofing will not be in place in the later stage.

    In addition, in the corner of the bathroom and the squatting toilet, be sure to work carefully, because these places are particularly prone to water seepage. When the waterproofing work of the toilet is done, the workers will also do water storage work on the bathroom. Generally speaking, the time of water storage work is about 48 hours, of course, some workers are more careful and will extend the time to 72 hours.

    When the time is up, we can take a look at how well the bathroom is waterproofed.

    The waterproofing work is done, and then the laying of wall tiles and floor tiles, as well as the installation of sanitary ware in the later stage.

  3. Anonymous users2024-01-22

    If you want to use bricks to build steps in the bathroom, you must wait for the bricks to be built before waterproofing, otherwise, waterproofing is done in vain. After the platform defense is built, the waterproofing of the sewage pipe mouth and the contact between the brick and the ground is done together, and then the squatting toilet is installed

  4. Anonymous users2024-01-21

    The problem of the bathroom is not so troublesome, and it is okay to do waterproofing after the squatting toilet is raised up the steps.

  5. Anonymous users2024-01-20

    It is best to do a good job of waterproofing the bathroom before installing the toilet.

  6. Anonymous users2024-01-19

    It should be waterproof first before making a squatting toilet, and the waterproofing of the bathroom is very important, so it must be done carefully.

  7. Anonymous users2024-01-18

    I think it should be waterproof first, so it would be better.

  8. Anonymous users2024-01-17

    I think it's better to do waterproof first and then do something else, so it would be better.

  9. Anonymous users2024-01-16

    I think you'd better do it waterproofing first and then get something else!

  10. Anonymous users2024-01-15

    It is also possible to make waterproofing after the squatting toilet has been raised up the steps.

  11. Anonymous users2024-01-14

    It is best to do a good job of waterproofing the bathroom before installing the toilet. I think it's better to do waterproof first and then do something else, so it would be better. I think it should be waterproof first, so it would be better.

    If you want to use bricks to build steps in the bathroom, you must wait for the bricks to be built before waterproofing, otherwise, waterproofing is done in vain. After the platform defense is built, the waterproofing of the sewage pipe mouth and the contact between the brick and the ground is done together, and then the squatting toilet is installedToilet waterproofing should be done before the installation of the squatting toilet, not after the installation of the squatting toilet.

    The drain of the toilet is inserted into the inside of the sewer pipe and has nothing to do with draining. Bathroom decoration must be waterproof first, for example, when doing the squatting pit platform, you must first do a good job of waterproofing, of course, you should also pay attention to waterproofing when doing the squatting pit platform. The bathroom should be waterproofed first and then done with others.

    2, is to do waterproof first, or press the squatting toilet first to do waterproofing, before the waterproof paint is painted, the ground wall should be cleaned, the uneven slope is too large to repair with cement slurry, and then do waterproofing, and then the ground should be a protective layer. Press the squatting toilet to do waterproofing first, and then do waterproofing after the squatting toilet is fixed.

  12. Anonymous users2024-01-13

    If the bathroom is not waterproofed first, is it okay to do the waterproofing after the squatting toilet is raised up the steps? It can be, but the effect is not good, because the water flows to the lower place, and the low place is the weak area, which is prone to problems. In addition, if the waterproof layer of the toilet is made too high, when it is higher than the floor of the indoor room, the water or moisture will seep into the room and return to moisture.

  13. Anonymous users2024-01-12

    No, you must do waterproofing first to ensure that there is no leakage in the sewer pipe, and only when the waterproofing is done well, can other auxiliary facilities be done.

  14. Anonymous users2024-01-11

    You need to do waterproofing first, and then install a squatting toilet, otherwise there will be water leakage.

  15. Anonymous users2024-01-10

    If the bathroom is not waterproofed first, it is okay to waterproof the squatting toilet after the steps are raised.

  16. Anonymous users2024-01-09

    There is a risk of water leakage.

    If the family population is small, it is okay to take a bath in the bathroom, but a few families, or individuals who use a lot of water for bathing and take a long time, will definitely leak to the downstairs.

  17. Anonymous users2024-01-08

    Summary. It's best not to, be sure to do waterproof first, otherwise the water leakage will be very troublesome later!

    If the bathroom is not waterproofed first, is it okay to do the waterproofing after the squatting toilet is raised up the steps?

    Hello, I have seen your question, and I am sorting out the answer, please wait for a while Oh It is best not to, you must do waterproof first, otherwise the water leakage will be very troublesome later!

Related questions
1 answers2024-08-28

Use the special glue and cement (and not too thin) to touch the joint of the pipe to solve the leakage.

16 answers2024-08-28

The sewer pipe is with a storage bend, choose the one without a water trap, the toilet seat sewer pipe does not go out to play where you need to use the toilet to go out to play, the sewer has a trap, if you choose a toilet with a trap two pure water inlets exist at the same time, the launching speed will be relatively slow in the process of launching, and there will be a bubbling phenomenon, and it will also affect the use.

3 answers2024-08-28

It's very simple, buy cans of putty (putty) in the building materials market and fill the gaps.

3 answers2024-08-28

Yes, there are two types of squatting toilets, such as the pit distance of your home before buying.

6 answers2024-08-28

In connection with real estate development, it may be related to the placement of the drain under the squatting toilet, which means that there is a problem with the trap under the drain pipe, or there is no trap at all. >>>More