What should be paid attention to in the acceptance of the kitchen and bathroom?

Updated on Kitchen 2024-08-01
5 answers
  1. Anonymous users2024-01-24

    1 all"Kitchen and bathroom acceptance.

    Method 1: Check the ventilation of the bathroom. Check whether the vent is reserved under the ceiling, if it is left on the ceiling, use a flashlight to check whether it has installation, and test the pumping force at the same time, and use a flashlight to check whether there is construction waste in the toilet vent; If the bathroom has windows in the corridor, anti-theft nets should be installed, and if there are no windows, ventilation holes should be installed.

    The ventilation hole is 10 cm in diameter and is located under the ceiling; The distance to the nearest socket to the vent should be. Kitchen and bathroom acceptance.

    Method 2: Inspect the quality of toilets and baths in the bathroom, including checking whether there are cracks in the toilet and bathware, and whether there is leakage in the bathtub, flush toilet, washbasin, etc., the cracks are sometimes as thin as hair, so they should be carefully observed; When accepting the toilet, it is necessary to see whether the drain is smooth, whether the flushing sound is normal, whether there is a leakage sound in the flushing tank, and whether the interface between the bathtub, basin and the wall or cabinet is waterproof.

    Kitchen and bathroom acceptance method 3: Whether there is a water leakage problem on the bathroom floor. Someone is taking a bath in the upstairs bathroom, and there may be a little dirty rain in the downstairs bathroom, because the upstairs waterproofing is not done well, so it is necessary to coordinate with the upstairs when accepting the bathroom and do a good job in the closed water test of each house. "

  2. Anonymous users2024-01-23

    The most important thing is the waterproof effect, the bathroom is built with cement ten centimeters high, the drain is sealed, and the water is filled for 24 hours. The downstairs is not leaky. Then the paving of wall tiles and floor tiles should be smooth, and the flatness of the ceiling.

    Electrical installation, reserved location of water pipes, and leveling.

  3. Anonymous users2024-01-22

    Are you home renovation acceptance? Bathroom and kitchen acceptance is mainly concealed engineering acceptance, waterproof water pipe circuit wiring is a hidden project must do a good job of acceptance, surface projects have ceilings and paving tiles and sanitary ware lamps installation these projects can be changed if they are not good, if the waterproof water pipe is broken, it is not good to repair, so the process supervision and concealed engineering to do a good job.

  4. Anonymous users2024-01-21

    I've done home improvement, the kitchen and bathroom are the most headaches, men may not know, it's a housewife's nightmare, and the most important problem is waterproof!

    First of all, when handing over the keys to the house, the property will take you to the room to check, you have to look carefully, there is a problem, he will help you solve it, when you want to decorate, he will help you do a waterproof experiment, remember, not in your home to do a waterproof experiment, but to your upstairs family to do, his kitchen and bathroom leakage, leakage directly to your home, and your downstairs residents, will come to your home to do waterproof experiments.

    Secondly, when looking for a decoration company, he will also help you do waterproofing, this is also the last one, must be done well, some decoration companies do not do well and even destroy the previous waterproof layer, so it is best to find a regular, large home improvement company, so that it is more guaranteed!

    Finally, of course, during the construction process, you have to supervise every day, home improvement is a very tiring thing, you have to watch how they do, which ones are not done well to put forward directly, when you go, you should also bring some greetings, people's hearts are made of meat, you give favors to others, will people not give you a good job?

    Happy decorating!

  5. Anonymous users2024-01-20

    1. The most important thing for the acceptance of the bathroom is that the waterproof layer must be done well, the qualified waterproof paint must be used and constructed in accordance with the standards, and the acceptance shall be carried out in accordance with the acceptance standards of the waterproof project (see the attachment at the end of this article: the acceptance of the waterproof project of the bathroom).

    2. The direction of the water pipes and wires in the kitchen and bathroom should be accepted before the tile is laid, especially after the hot and cold water pipes are connected, the inlet pump pressure test should be carried out for 48 hours, and the leakage should be eliminated in time.

    3. The drain of the bathroom floor drain and the drain of the toilet should be plugged when laying floor tiles to prevent cement from falling into the sewer pipe and causing poor sewerage in the future. The floor drain of the toilet and the floor drain of the bathroom should be at the lowest point so that no water will accumulate.

    4. The ventilation of the kitchen and bathroom should be smooth, and the exhaust fan should ensure that there is enough suction.

    5. The bathroom should be closed water test, all the floor drains should be blocked, and then the bathroom floor should be filled with water, keep it for 24 to 48 hours, and observe that there should be no leakage in the downstairs bathroom, indicating that the waterproof is qualified.

    6. The location and quantity of all power sockets should meet the requirements.

    Attached: Acceptance of waterproof works in the bathroom.

    1.Waterproof construction should be used for coating film waterproof materials.

    2.The performance of waterproof materials shall comply with the provisions of the current national standards, and there shall be a product qualification certificate.

    3.The surface of the base should be smooth, and there should be no defects such as hollowing, sanding, and cracking. The moisture content of the base layer should meet the construction requirements of waterproof materials.

    The waterproof layer should extend from the ground to the wall, 250mm above the ground. The height of the waterproof layer on the bathroom wall shall not be less than 1800mm.

    4.The waterproof cement mortar screed layer is densely combined with the foundation, without hollowing, the surface is smooth and clean, no cracks, sanding, and the yin and yang angles are made into an arc.

    5.The waterproof layer of the coating film is evenly brushed, and the thickness meets the requirements of the technical regulations of the product, and the general thickness is not less than the bottom.

    6.The use of construction stubble should be lapped in the direction of flowing water, and the lap width should not be less than 100mm, and more than two layers of fiberglass cloth should be staggered by half of the width when lapping up and down.

    7.The surface of the coating film is not blistered, does not flow, is smooth and has no concave and convex, and the joints of pipe fittings, sanitary ware feet, floor drains, and drainage outlets are tight, and the end is smooth and does not leak.

    8.The thickness and strength of the protective layer cement mortar must meet the design requirements, and it is strictly forbidden to destroy the waterproof layer during operation, and the ground flooding slope should be done according to the design requirements, and the drainage should be smooth, and there should be no water accumulation.

Related questions
2 answers2024-08-01

Process requirements.

1) The floor of the bathroom must be compacted, wiped with the beating, compacted and wiped to form a waterproof layer of its own. >>>More

1 answers2024-08-01

1: Whether the original waterproof layer has been damaged. >>>More

2 answers2024-08-01

Don't ignore these in the kitchen decoration: 1. If there is a pillar in the kitchen, it should be used as a partition, open up a special area for babies, and store tableware and milk powder; 2. The Chinese woks are high, and it is recommended that the stove is 4 cm lower than the operating table; 3. The kitchen is small, and the wall is fully stored; 4. There is a cabinet under the light, cutting vegetables without backlight, and intelligent control is very convenient; 5. Children's lock to prevent children from turning over dishes and accidents.

8 answers2024-08-01

The bathroom should be separated as much as possible. The benefit of functional area separation is that each function can be used separately without being disturbed, and the use efficiency of the entire bathroom is improved.

5 answers2024-08-01

1.Doorsill.

The threshold is a checkpoint to prevent water from overflowing from the bathroom, and its design and construction points are: the upper plane of the threshold should be inclined to the inside of the bathroom, so that the water droplets can slide smoothly to the inside of the bathroom; The threshold should be the same width as the door frame, and the door frame should be the same thickness as the wall, so that there will be no big discrepancies when laying floor tiles, and the chance of breaking is relatively reduced. >>>More