Do the bathroom waterproof first or do the squatting pit platform first

Updated on Bathroom 2024-08-07
5 answers
  1. Anonymous users2024-01-24

    The bathroom is generally backfilled first and then waterproof, the bathroom waterproof, is to prevent the ground water from leaking down, if it is reversed, waterproof below, the ground water will still leak into the backfill, resulting in the backfill continues to absorb water, the ground is hollow, and the ground is wasted.

  2. Anonymous users2024-01-23

    First backfill and then waterproof construction, toilet waterproofing, is to prevent the ground water leakage.

    If it is upside down and waterproof below, the ground water will still seep into the backfill, resulting in the backfill continuing to absorb water, the ground is hollow, and the ground is wasted. . .

  3. Anonymous users2024-01-22

    Make the squatting pit platform first and then do the waterproofing, but the waterproofing of the squatting pit platform must be done well.

  4. Anonymous users2024-01-21

    Make the height first, and then make the waterproof.

  5. Anonymous users2024-01-20

    Waterproofing first, and then backfilling is what you're talking about.

Related questions
2 answers2024-08-07

Do waterproofing needs to be done on the surface of the water, dig excellent permeability crystalline waterproofing, you can do it yourself on the cement surface with a super permeable waterproof guard (if there are cracks and potholes on the cement surface, fill the complete with metin porcelain glue and then do waterproofing). >>>More

2 answers2024-08-07

If you don't do waterproofing first, the gap between the partition and the ground will leak later, so be sure to do waterproofing first.

15 answers2024-08-07

Do you do waterproofing or underfloor heating in the bathroom first? >>>More

3 answers2024-08-07

Do waterproofing first, it is best to use waterproof materials with water, and then paste tiles after confirming the effect, otherwise you have to rework.

11 answers2024-08-07

The bathroom decoration should first do the water pipe arrangement, and then make the waterproof layer. According to the rules of the house decoration construction process, the entry of workers into the site is always the first step. If the waterproofing is completed first, then the subsequent construction arrangement of the water pipe, such as slotting and drilling, will inevitably damage the waterproof layer, thus forming a hidden danger of water leakage. >>>More