What should be calculated for the amount of toilet water supply and drainage engineering?

Updated on Bathroom 2024-08-05
3 answers
  1. Anonymous users2024-01-24

    If it is a budget consideration, there are generally as follows: 1. The material, specification and quantity of water supply and drainage pipes; 2. Specifications and quantities of valves and angle valves; 3. The number of sanitary ware specifications; 4. The number of pipe supports; 5. If it is a concealed pipeline, the number of wall planing ditches and casing should also be considered; 6. Auxiliary materials for various pipeline assembly, etc. Hope it helps!

  2. Anonymous users2024-01-23

    The number of pipes, the number of sanitary ware, the number of hardware gate valves.

  3. Anonymous users2024-01-22

    Look at the descriptions of the chapters in the budget quota, there are detailed explanations, if you can't understand the quota, then what kind of budget do you have?

    The calculation of the engineering quantity of the quota in each province is different.

Related questions
1 answers2024-08-05

The installation of toilet equipotential boxes implements the general junction box installation quota, and the material cost is calculated separately according to the actual situation. If the grounding wire welding to the equipotential box uses the main reinforcement in the civil ring beam, the base price of the equalizing ring laying sub-item can be multiplied by the coefficient, and if a separate flat steel or round steel is used, the quota of "indoor grounding bus laying" can be implemented. If there is a steel plate, the iron plate can be calculated according to the iron component production, installation, and calculation.

3 answers2024-08-05

Theoretically, it should be deducted, but in practice, the place where the squatting pit is reserved, the floor tiles are to be cut in an arc, which increases the workload, and the collage is more complicated than other places, so generally for the convenience of calculation, the area is not deducted. It doesn't cost much money to process, and it is calculated evenly, after all, it occupies a small area.

3 answers2024-08-05

The drawing is written below that the plate thickness is not indicated as 110, if the bathroom and balcony are not indicated in situ, then the bathroom and balcony plate thickness is 110, and the bathroom and balcony are 50 lower than the floor, which means that the bottom of the bathroom and balcony is 50 lower than the bottom of the floor, so that although the plate thickness is 110, the effect of the bathroom and balcony is 50 lower than the floor. But if you take a closer look, the thickness of the bathroom board should be thinner.

1 answers2024-08-05

The bridge is calculated by meters, and the joints are calculated separately. The volume of the septic tank atlas is calculated according to the corresponding volume, and the volume of the septic tank atlas exceeds the volume of the septic tank atlas, which is calculated according to the structure item, and the building quota corresponds to the subheading. Of course, it's the area. >>>More

1 answers2024-08-05

It should be calculated twice, because it includes the cost of labor and materials, and it is reasonable to count it twice.