  1. Anonymous users2024-01-24

    1.Uneven ceiling: The reason is that the boom is not leveled carefully when the large keel equipment is used, and the elevation of each boom point is inconsistent. During construction, the tightness of each hanging point should be checked, and the connection line should be connected to check whether the elevation and flatness meet the needs of the plan and construction specifications.

    2.Some node plans of light steel skeleton are unreasonable: in the holes, lamp openings, vents, etc., keels and connectors should be set according to the corresponding node plan of the drawing, so that the plan meets the needs of the atlas and the plan.

    3.The light steel skeleton is not firmly hoisted: the light steel skeleton of the roof should be hung on the main plan, and the boom nut should be tightened to control the elevation of the fixed plan; The pipelines and equipment parts in the ceiling shall not be hoisted on the light steel skeleton.

    4.The gap between the blocks of the cover panel is not straight: pay attention to the plate specification during construction, align the cable, and ensure that the equipment is flat and straight when it is fixed.

    5.The seam strip and edge strip are not tight and straight: the line should be pulled during construction, and it should be fixed and pressed after alignment.

    6. Heavy lamps, fans and other heavy equipment greater than 3kg are prevented from being on the keel of the ceiling project.

  2. Anonymous users2024-01-23

    1.The reason for the unevenness of the light steel keel ceiling is that the boom is not leveled seriously when the large keel is installed, resulting in the inconsistent elevation of each boom point. During construction, the tightness of each hanging point should be checked, and the connection line should be connected to check whether the elevation and flatness meet the requirements of the design and construction specifications.

    2.The local node structure of the light steel skeleton is unreasonable: in the holes, lamp openings, vents, etc., the keel and connectors should be set according to the corresponding node structure of the figure, so that the structure meets the requirements of the atlas and design.

    3.The light steel skeleton is not firmly hoisted: the light steel skeleton of the roof should be hung on the main structure, and the boom nut should be tightened to control and fix the design elevation; The pipelines and equipment parts in the ceiling shall not be hoisted on the light steel skeleton.

    4.The gap between the blocks of the cover panel is not straight: pay attention to the plate specifications during construction, align the cable, and ensure that it is straight and straight when installed and fixed.

    5.The seam strip and edge strip are not tight and straight: the line should be pulled during construction, and it should be fixed and pressed after alignment.

    Problems encountered in the construction of light steel keel gypsum board ceiling should be actively solved in a timely manner, and the heavy should not be avoided, resulting in losses.

  3. Anonymous users2024-01-22

    Let me introduce you to the installation of the Knauf ceiling system.

    1. First look at the installation of the Yanbian keel. First of all, the L-shaped extended keel is installed at the required height, and it is fixed on the wall with screws, and the spacing of the screws is 600mm.

    2. Installation of hanging parts. The boom is fixed to the ceiling of the building, but the boom can be bent according to the actual situation and cut to a suitable length, so as to facilitate the installation of the ceiling pendant.

    3. Installation of upper and lower C-shaped keels. Let's start with the upper C-shaped keel, which is installed at a time distance that depends on the load that the ceiling system needs to bear. The installation of the lower C-shaped keel is combined with the wall, so it is not in a hurry to fix.

    Here are some small insights of my own, I hope it will be helpful to you.

  4. Anonymous users2024-01-21

    Light steel keel gypsum board ceiling or wood keel ceiling must be constructed in accordance with the standard process.

Related questions
3 answers2024-07-06

Some are wooden keels. Some use light keel, general tooling uses light keel, home decoration now uses light keel, and there are more wooden keels. >>>More

1 answers2024-07-06

It's the same as painting a decorative drawing, what a plane elevation, a top surface, a section, a large sample. >>>More

3 answers2024-07-06

Are you asking whether a light steel keel ceiling or a wooden keel ceiling is better? Personally, I think that it is better to improve the home or the wooden keel, and the light steel keel that is mandatory in public places.

4 answers2024-07-06

The cost price in Xi'an is 50 yuan square meters, excluding the price of scraping putty and brushing latex paint.

3 answers2024-07-06

The spacing of the main keel is usually 900 1200, the secondary keel covered keel is 400 * 400, or 400 * 600, the side keel is the perimeter of the wall, the grille lamp and the maintenance port and the air conditioning Wang tuyere will have the keel strengthened, the ordinary decoration gypsum board with a single layer, the fine decoration gypsum board low with a double layer, the early high level with a single layer of 12 thick Lu Lingqin, there is a modeling ceiling, the amount of gypsum board is calculated plus loss.