Floor mounted scaffolding balcony can not be used in a single row

Updated on Balcony 2024-07-21
1 answers
  1. Anonymous users2024-01-24

    Floor-mounted double-row scaffolding more than 24m belongs to the more dangerous sub-items, and special construction plans need to be prepared. More than 50m is a dangerous sub-item of more than a certain scale, which needs to be demonstrated by experts.

    Cantilever scaffolding is mainly a structure that has no time to backfill earthwork, and the floor-mounted scaffolding erected by the foundation is generally dismantled at about 2 floors, and the cantilever scaffold is erected at the same time. According to the specification, cantilever scaffolding more than 20m is a sub-item with greater danger of exceeding a certain scale, which requires expert argumentation and is more troublesome.

    This problem has just been said, erection to 50m earthwork backfill can not be constructed, foundation and foundation acceptance can not begin. Therefore, when the construction reaches the 2-3 floors, it will start to turn to the cantilever scaffolding.

Related questions
2 answers2024-07-21

There are a lot of them, and there are big ones such as Yuantuo Group. >>>More

1 answers2024-07-21

Since it's protection, why connect the scaffold?

2 answers2024-07-21

The floor-to-ceiling balcony is shown in the picture below

2 answers2024-07-21

The use of aluminum alloy single-tube scaffolding can easily solve the cantilevered scaffolding.

4 answers2024-07-21

It is not possible to go through formal channels, it belongs to the façade renovation, and it must be approved by the Planning Bureau and the Housing and Urban-Rural Development Bureau. If you renovate yourself, no one complains to the Planning Bureau and the Housing and Urban-Rural Development Bureau, or if you can communicate with them well, there is no big problem.