  1. Anonymous users2024-01-24

    There are several construction points to pay attention to in toilet waterproofing: the base layer should be handled well and kept smooth and clean; When painting a large area, it is necessary to use a cross method to apply thin and multi-brush; The detail node should be trowelted; After the construction is completed, a closed water test must be done to check whether the waterproof layer is qualified. In fact, it is still more complicated to do waterproofing, and the technical requirements for construction personnel are also relatively high.

    Yuhong waterproofing service team is professional, many people around me are looking for Yuhong waterproof to do, a very famous brand.

  2. Anonymous users2024-01-23

    1. Bathroom waterproof construction steps.

    Step 1: You can use a slightly coarser cement to base the foundation first, and then brush the waterproof paint after the cement is dry. But in painting money, the ground should be flat and there should be no grooves. Water is then sprinkled on the ground to expel the gas from the small holes.

    Step 2: Mix the powder and liquid material evenly, and brush the bubbles if there are bubbles when brushing the paint.

    Step 3: When brushing the paint, brush it from the same direction, wait 1-2 hours, and then brush the second coat. When brushing the second layer, the direction of the brush should be opposite to that of the first layer, so that the best coverage can be achieved.

    Step 4: You can brush it several times, which can increase the density and fill the gaps. Some people think that the more layers of waterproof paint the better, or even brush six or seven layers, but in fact, this is not good, the paint is too thick and easy to crack.

    Step 5: Wait for one day before taking a waterproof test.

    Step 6: When doing the waterproof test, you should first fight with your downstairs neighbor.

    Say hello, then plug the drain, fill the ground with water, and wait an hour to ask your downstairs neighbor if there is a leak. If there is a water leak, the waterproofing layer should be rebuilt. If the waterproof test is qualified, it can be tiled.

    2. Precautions for waterproofing in the bathroom.

    1. In order to ensure that the bathroom floor is flat, it must be leveled with cement mortar, and then waterproof, so as to avoid leakage caused by uneven thickness of waterproof coating.

    2. After leveling, when carrying out the construction of the waterproof layer, it is necessary to pay attention to fire prevention and waterproofing.

    3. When doing waterproof construction, the floor drain, pipeline, and wall hole should be carefully inspected, and the root of the pipeline must be caulked according to the requirements during construction. 4. The waterproof treatment of the wall should also be noted, if the wall and the bathtub are adjacent, then the waterproof treatment height should be higher than the upper edge of the bathtub, and the shower should reach a height of 180cm.

    5. Before doing waterproofing, pay attention to the correct position of the floor drain elevation.

    6. To ensure that the sewer is smooth, the sewer pipes in the bathroom, including floor drains and toilet sewer pipes, must be kept unobstructed.

  3. Anonymous users2024-01-22

    How to do toilet waterproofing work well? Bathroom waterproofing should be constructed in accordance with the standard process and process The effect is good Waterproof standard process flow (key points): Grassroots cleaning The wall root and the perimeter of the pipeline need to do a waterproof additional layer Painting Closed water test Waterproofing is a hidden project, is the top priority of foundation construction, landscape decoration reminds everyone to pay attention to the following points when accepting:

    First, the waterproof layer on the ground should extend to the wall surface back 30cm, the waterproof layer of the wall in the shower or connected room shall not be less than 2000mmX1200mm, and the waterproof height of the bathtub wall shall not be less than 1400mm; Second, the waterproof layer of the wall needs to be brushed and then tiled, and the air defense drum should be affixed; Third, the ground waterproofing needs to be closed for 24 hours, and there is no leakage; Fourth, the whole brick wall must be painted with special tile adhesive on the back of the brick. How to do bathroom waterproofing work well, now do you know the answer?

  4. Anonymous users2024-01-21

    How to do toilet waterproofing with red waterproof? How to do toilet waterproofing? You can use the glue directly, clean the ground with the glue, and brush the glue.

    Yuhong waterproof is good or not, the quality is very good, you have to brush 2 or 3 times, and clean up the things on the ground.

Related questions
3 answers2024-06-02

Yuhong waterproof maintenance efficiency is really high, my toilet leakage is also very serious, after looking for Yuhong waterproof, the next day someone came to investigate the situation, develop a maintenance plan, and quickly get it.

1 answers2024-06-02

First of all, there is no settling tank on the bathroom floor, if there is no settling tank, you can use polymer with white cement to brush the ground, but it is not recommended to use it like this, the general ground is recommended to do one-component polyurethane waterproof coating, you can use rainbow SPU-301

4 answers2024-06-02

Water leakage should be solved quickly, find the source of water leakage, and strengthen the waterproof layer.

5 answers2024-06-02

Bathroom waterproof materials can be waterproof coatings; Yuhong waterproof coating is good.

15 answers2024-06-02

Hello, Apple Decoration will answer the toilet waterproof construction process for you: