What should be installed before the decoration and suspended ceiling?

Updated on Suspended ceilings 2024-06-13
3 answers
  1. Anonymous users2024-01-24

    civil works, tiles, plumbing renovations, and then suspended ceilings.

  2. Anonymous users2024-01-23

    Water, electricity, ground!

  3. Anonymous users2024-01-22

    Where are you???

Related questions
4 answers2024-06-13

If the smoke pipe is buried in the ceiling, the smoke pipe should be embedded before the ceiling, and the ceiling and the cabinet do not conflict, but the most comfortable order is: embedded smoke pipe - ceiling - cabinet - smoke machine stove! It's okay to hang the ceiling first, and it's very convenient to dismantle the ceiling!

4 answers2024-06-13

When decorating, we should choose to carry out the ceiling first, which can save a lot of trouble. There are three reasons for laying the ceiling first and then laying the floor tiles: first, the protection of the finished product; Second, the renovation time can be shortened. Third, the quality of construction can be guaranteed. >>>More

2 answers2024-06-13

Home renovation is to install the ceiling first. Before the installation of the integrated ceiling, there is no pre-embedded smoke pipe, which will lead to a series of problems such as small suction power of the range hood, high noise during machine operation, severe machine shaking, oil accumulation, oil leakage and smoke smell in the public flue. >>>More

2 answers2024-06-13

It must be the ceiling first, and then the cabinet is installed after the ceiling is completed.

2 answers2024-06-13

You should put tiles first, and then choose the toilet, which is a correct installation procedure, and will also get a good decoration for the bathroom in your home.