If the bathroom is waterproof, the marked riser part must be sealed with water first? Then brush it

Updated on Bathroom 2024-06-11
1 answers
  1. Anonymous users2024-01-24

    The waterproof construction of the toilet focuses on the node treatment of the root of the pipe, the yin and yang corners of the wall, and the threshold part.

    The red line in the diagram focuses on all the pipe roots at the ground, including floor drains and water mains. First of all, it is brushed with water, and then paved with "propylene (acrylic) polymer waterproof" material.

    After the construction is completed, it needs to be cured for one to two days, and then do a "closed water test", and no leakage within 24 hours is considered qualified.

Related questions
4 answers2024-06-11

1.The bathroom should be waterproof first (generally the developer has done waterproofing when handing over the house, in order to prevent building quality problems, it is recommended to do it again to rest assured) and then package the riser! >>>More

4 answers2024-06-11

You can, mainly look at the process, from the perspective of safety and simplicity, first waterproof, and then package the pipe, you also need to do one thing, after doing the waterproofing, put the pipe around the pier of a platform about 2 cm, and then wrap the pipe around the platform to prevent water ingress, and there is a peculiar smell after a long time.

2 answers2024-06-11

Home decoration waterproofing is to go through water and electricity first and then do waterproofing. The installation of water and electricity will damage the cement base surface, resulting in the destruction of the original waterproof layer made by the developer!

2 answers2024-06-11

If you don't do waterproofing first, the gap between the partition and the ground will leak later, so be sure to do waterproofing first.

3 answers2024-06-11

Do waterproofing first, it is best to use waterproof materials with water, and then paste tiles after confirming the effect, otherwise you have to rework.