After the bathroom pipe hole is not reserved, how to deal with the waterproofing of the hole

Updated on Bathroom 2024-05-24
5 answers
  1. Anonymous users2024-01-24

    After doing it, just seal the ground with cement sealing, and sealing glue can be sealed, and the sealing glue is generally sold in hardware stores.

    Toilet waterproofing construction practices:

    1. Ground treatment.

    Before waterproofing, be sure to level the ground, if the ground is uneven, it may affect the effect of waterproofing, and may also cause cracking and leakage caused by uneven thickness of waterproof coating. Floor drains, wall corners, pipe heels and other joints should be painted with high elasticity and flexible waterproofing, because the joints between the wall and the floor of the bathroom will be displaced, and water seepage is most likely to occur.

    2. Wall treatment.

    If the bathroom has a shower room, the waterproof should be 180cm, and if there is a bathtub, the waterproof height of the wall adjacent to the bathtub should be 30cm higher than the bathtub

    3. After the waterproof layer is done, a certain amount of time should be left to make the waterproof layer better integrated with the building, and then the protective layer on the waterproof layer and then paved the floor tiles.

    4. Waterproof construction is a concealed project, and the follow-up construction may also damage the waterproof layer, if the floor tiles have been laid, do not smash the floor tiles, use professional waterproof materials to plug all the gaps and do a good job of waterproofing. It is also suitable for waterproofing projects after the failure of the waterproof layer in the bathroom.

    5. Waterproofing is a systematic project, and the causes and treatment methods are different in each place. Materials are the foundation, construction is the key, and follow-up service is the guarantee.

    Preparation Reinforced concrete floor slabs.

    1:3 cement mortar to find the slope layer, slope to the floor drain, a smoothing.

    Acrylic waterproofing, polymer cement waterproofing or polyurethane waterproofing.

    30mm thick dry hard cement mortar bonding layer.

  2. Anonymous users2024-01-23

    If it's not a big problem, just seal the ground after you're done.

  3. Anonymous users2024-01-22

    Sealing with cement and sealing glue can be sold in hardware stores.

  4. Anonymous users2024-01-21

    When you're done, just seal the ground.

  5. Anonymous users2024-01-20

    The gap in the pipe needs to be filled and leveled first, and the bathroom is generally waterproofed with mortar waterproofing agent, so leveling and filling the void can also be directly used with mortar waterproofing agent, and then waterproofing can be done.

Related questions
5 answers2024-05-24

If the construction hole is not properly treated, cracks will form around it. In order to prevent the occurrence of cracks, the following construction techniques should be observed in addition to the above-mentioned filling methods. >>>More

3 answers2024-05-24

Drains and floor drains, and some also mop pool drains, as well as exhaust outlets.

5 answers2024-05-24

The hose of the normal exhaust fan is 100, press this to leave it.

3 answers2024-05-24

It shows that the hole wall contains more water.

4 answers2024-05-24

No, the exhaust duct must be separated and the two openings must be separated, as the air in your back kitchen will be polluted when there is a headwind.