The bathroom water storage test is not required to be done in every room

Updated on Bathroom 2024-05-28
1 answers
  1. Anonymous users2024-01-24

    The water storage test of the bathroom is to test the sealing of the waterproof coating of the bathroom, so each bathroom should do the water storage test after the waterproof painting is completed;

    If the other rooms are bedrooms, living rooms, etc., there is no need to do it; Where there is no floor drain, the water storage test cannot be discharged;

    Note: After the water storage test, the ground or wall shall not be grooved or rectified to avoid damaging the waterproof layer;

    Therefore, before making the waterproof layer, it is required to rectify the ground sewage pipes of the bathroom, and some pipes on the wall should also be rectified in place.

Related questions
1 answers2024-05-28

Under normal circumstances, the water storage test in the bathroom at home takes a day, and it is best to extend the time if you redo the waterproofing.

5 answers2024-05-28

The main thing is to store water for 24 hours, notify the downstairs before doing it, and pay attention to observe whether there is a leakage, if not.

1 answers2024-05-28

As long as there are no signs of water leakage downstairs, and there are no signs of water leakage below the building for a long time, this shows that the waterproofing is very successful, and there is no weak impact

2 answers2024-05-28

Check if there is a problem with the sewer pipe.

Is it a new building. >>>More

2 answers2024-05-28

Yes, because they can all be written on the same layer.