Can the bathroom be tiled immediately after waterproofing? How much of an impact

Updated on Bathroom 2024-04-02
8 answers
  1. Anonymous users2024-01-23

    No! Absolutely not! If you want to achieve the best waterproofing effect, you can only wait until the waterproof layer is completely dry before you can apply tiles!

  2. Anonymous users2024-01-22

    After being sure to try the waterproofing, I put it on the tile. Look at what kind of material your home is made of Qing mold bad code ant waterproof.

    If the leakage is the waterproofing of the mortar, it can be directly tiled.

    If not, it must be brushed with cement slurry first.

    Otherwise, it won't stick.

  3. Anonymous users2024-01-21

    Before the decoration and brick laying of the bathroom or kitchen room, regardless of the original or new waterproof layer, a 24-hour full water test must be done during the insurance period.

    Fill about 50mm of water in the water room, and after 24 hours there is no leakage, the bricks can be laid, and it is easy to divide the responsibility; After laying the bricks for about 2 days, do a water splashing test to check whether the ground drainage slope of the water room meets the requirements, and whether there are any defects that affect the use such as water accumulation, reverse slope, and floor drain leakage.

    After being sure to try the waterproofing, I put it on the tile. And it also depends on what material your home is waterproof, if it is the waterproofing of mortar, it can be directly tiled. If not, it must be brushed with cement slurry first. Otherwise, it won't stick.

  4. Anonymous users2024-01-20

    In general, there should be a curing period of five to seven days after the waterproof layer is done, so the tile should be done after five to seven days, and the waterproof layer should be protected between this option, especially when the tile is pasted, it is necessary to pay attention to protect the waterproof layer.

    There are often disputes between the upper and lower neighbors because of water leakage, and the problem is mainly due to the failure to do a good job of waterproofing in the masonry stage. There are several things to pay attention to when doing waterproofing, one is that the ground and wall should be cleaned first, and the gaps and grooves should be filled and smoothed; Second, the wall of the shower position should be brushed high; the third is to do carefully at the floor drain and squatting interface; Fourth, do a good job of closed water test, the test time should be more than 24 hours, and the owner can only sign it after accepting it himself.

  5. Anonymous users2024-01-19

    After being sure to try the waterproofing, I put it on the tile. See what material your home is waterproof, if it is waterproof mortar, you can directly paste the brick.

    If not, it must be brushed with cement slurry first.

    Otherwise, it won't stick.

  6. Anonymous users2024-01-18

    The key to whether it can be tiled immediately is that the quality of the waterproofing agent is related to the quality of the painting process. As for whether there will be water leakage, no one can say, mainly based on the 24-hour water storage test. According to the construction requirements, it is necessary to wait for no leakage before tiling.

    Otherwise, if you find that there is another leak, you will have to knock off the tile.

  7. Anonymous users2024-01-17

    After being sure to try the waterproofing, you can paste the tile immediately if you want to paste it, and the life is shorter, and it will not.

  8. Anonymous users2024-01-16

    That depends on the degree of drying of your first brush, and the second time the water must be dry, and after doing a 24-hour water test to confirm that there is no leakage, you can pave it.

Related questions
1 answers2024-04-02

The bathroom can survive the winter, and the waterproof mainly plays a role in not leaking downstairs

2 answers2024-04-02

To do waterproofing, you need to do it on the front of the water. >>>More

1 answers2024-04-02

Dig the best permeable waterproofing can be done by yourself. >>>More

2 answers2024-04-02

No.

In humid environment, the plate can not be used as the keel of the partition beam and support, which is easy to deform when damp, and the tiles on it will cause the tiles to crack and loosen and fall off. >>>More

2 answers2024-04-02

Yes, there are waterproof membranes specifically for color steel, and lap joints can be partially or fully paved.