It doesn't matter if the top of the first hanging cabinet has an analysis, and it is okay to install a decorative sleeve on the edge, which does not appear rigid.
-
The cabinet can be covered with a gap before the ceiling is installed, and the cabinet is generally equipped with a five-millimeter construction gap, which can be covered with sealant. It is better to make cabinets first.
It must be suspended first, and the cabinets must be installed after the wall tiles are pasted - this is the general procedure for decoration construction. Otherwise, it will not only affect the construction of the ceiling, but also may damage the cabinets, and there will be a lot of dust、、、 when the painter is about to finish, it is not too late to install the cabinets.
The order is wall tiles, ceilings, floor tiles at one time.
The decoration construction follows the basic principle of "whoever is dirty first", and the construction sequence of the ceiling and brick laying will vary depending on the space. >>>More
First do hydropower, then do waterproofing.
After the water and electricity are done, fill the gap between the floor and the water pipe, and then do the waterproofing. >>>More
According to the specific situation, the gas water heater should be installed last. >>>More