What is the order of the ceiling and putty scraping when decorating

Updated on Suspended ceilings 2024-02-18
8 answers
  1. Anonymous users2024-01-23

    Hang the ceiling first, and then scrape putty.

    The hard decoration of decoration is divided into "water, electricity, mud, wood and oil" according to the type of work.

    1) Plumber.

    The house decoration first carries out water and electricity positioning, water and electricity wiring.

    2) Masons (bricklayers), carpenters.

    The completion of water and electricity is done by masonry and carpentry at the same time, but there are still some successions;

    Where there is no need for bricklayers, carpentry is done, but the kitchen is still bricklayered, and the wall and floor tiles are being pasted and carpentry is being done to make cabinets.

    3) Oilman. After the carpentry is finished, it is the painter's treatment of the base layer of the wall, that is, the batch of putty; Then the primer is applied, and the first coat of topcoat is applied;

    After the first topcoat is completed, you can carry out the installation of the overall finished thing, remember to protect the ground for some projects on the ground, and you can carry out the last topcoat painting when the installation is basically over.

    The ceiling you are talking about belongs to carpentry and should be completed before the oiler (batch putty).

    Note: The order of each company is slightly different, please note that the arrangement of each construction team leader of each company applies.

  2. Anonymous users2024-01-22

    Suspended ceilings, scraping putty, sticking wallpaper, you said these three orders are correct. Now that the putty has been scraped, you can scrape the ceiling and polish it uniformly. One primer and two topcoats, (wallpaper walls can be pasted without topcoat).

    After cleaning up, you can paste wallpaper. Thank you for adopting.

  3. Anonymous users2024-01-21

    After the start of construction, the wall renovation in the house will be rectified, for example: the wall will be demolished here, and the wall will be newly built here;

    When the wall is renovated, the plumber slots the water and electricity wiring in the house, and the end of the slotting is the wiring, and the wiring is the powder trimming trunking;

    The completion of water and electricity is done by bricklayers and carpenters at the same time, but there are still some successions; Where there is no need for bricklayers, carpentry is done, but the kitchen is still bricklayered, and the wall and floor tiles are being pasted and carpentry is being done to make cabinets.

    After the carpentry is finished, it is the painter's treatment of the base layer of the wall, that is, the batch of putty; Then the primer is applied, and the first coat of topcoat is applied;

    After the first topcoat is completed, you can carry out the installation of the overall finished thing, remember to protect the ground for some projects on the ground, and you can carry out the last topcoat painting when the installation is basically over.

    Note: The order of each company is slightly different, please note that the arrangement of each construction team leader of each company applies.

  4. Anonymous users2024-01-20

    The order of our company: first hanging shed - wall treatment cracks - mending the wall - scraping putty twice - sandpaper sanding - brushing latex paint twice.

  5. Anonymous users2024-01-19

    Of course, it is to do the carpentry ceiling first, and then do the construction of scraping putty and brushing paint.

  6. Anonymous users2024-01-18

    The most common ceiling is to use gypsum board to suspend the ceiling, and the gypsum board is also to be treated with white and putty powder. Therefore, if you use gypsum board to suspend the ceiling, you need to first suspend the ceiling and then scrape the putty.

  7. Anonymous users2024-01-17

    The decoration should be done first with wall treatment and then with a suspended ceiling.

  8. Anonymous users2024-01-16

    First plumbing, then bricklayers, carpenters, painters.

Related questions
1 answers2024-02-18

First modify the water and electricity, then lay the floor, then carpenter the decoration and paint, and finally install the lamps and lanterns!

2 answers2024-02-18

The wallpaper is for the wall to look good, dirty and easy to take care of, the ceiling does not need to be wallpapered, scrape putty and brush latex paint.

1 answers2024-02-18

Everything else is fine, but the doors and windows should be installed after the water and electricity are finished, otherwise they will be inappropriate to connect with the walls and floor tiles.

3 answers2024-02-18

Wood grating ceilings belong to the customized category of finished ceilings, which are available in wood fiberboard and PVC, which can be found in the building materials market.

2 answers2024-02-18

In order to be able to install other lamps other than ceiling lamps, there are many suspended ceilings for the sake of aesthetics. >>>More