Is the kitchen to have an integrated ceiling or cabinets first?

Updated on Kitchen 2024-01-27
9 answers
  1. Anonymous users2024-01-23

    Do the integrated ceiling first.

    If the smoke exhaust pipe of the smoke extractor is designed on the integrated roof, and there is no gap between the top of the cabinet and the integrated roof when you want to install the cabinet, it is best to hang the roof first, so that when we install the cabinet, we can control the height and gap of the installation very well, and the effect is also more beautiful.

    If the smoke exhaust pipe of the hood is designed under the integrated roof, this situation must be suspended first, because of this design, the height of the integrated ceiling crane is relatively high, and the kitchen wall cabinet also has an installation height, so that there will be a large gap between the cabinet wall cabinet and the integrated roof.

  2. Anonymous users2024-01-22

    Our home is to install cabinets first, and then install the ceiling, because the pipe of the smoke machine and the pipe position of the water heater are determined first, and when the ceiling is installed, the aluminum gusset will be cut according to your pipes, please enter.

  3. Anonymous users2024-01-21

    1.The normal is to install the ceiling first, after the ceiling is installed, determine the height of the entire cabinet, our wall cabinet can not lean on the top of the wall cabinet, to avoid sanitary dead ends.

    2.If you install the cabinet first and then install the integrated ceiling, there is a lot of garbage in the process of decoration and there is no way to clean up the cabinet.

    3.The installation sequence of the ceiling is relatively simple and can be completed in one day.

    Therefore, it is generally necessary to install the ceiling first and then install the cabinets.

  4. Anonymous users2024-01-20

    Generally, it is to do a good job of installing cabinets on the ceiling, and the opening of the range hood generally does not pass through the ceiling, if there is a conflict, in fact, it is mainly based on their own situation to choose, and the process does not affect which one to do first.

  5. Anonymous users2024-01-19

    According to the decoration order, the principle of first difficult and then easy, first up and then down, first inside and then outside. Install the ceiling first, and then install the cabinets.

  6. Anonymous users2024-01-18

    Of course, it is to make the ceiling first, and then make the cabinet. Reserve the position of the range hood.

  7. Anonymous users2024-01-17

    First suspend the ceiling, let the kitchen cabinet give you a drawing, and the worker ceiling will mark the location of the reserved hole according to the above.

  8. Anonymous users2024-01-16

    Your cabinet plan is set, ask the designer to give you a range hood ceiling opening position, and then you put the location (drawings to the ceiling shop), so that the ceiling shop itself will reserve the opening for you, generally the cabinet has not been done, the ceiling has been installed, because the cabinet is slow, the ceiling is piece-by-piece, directly used.

  9. Anonymous users2024-01-15

    Our house first install cabinets, install the ceiling, because the smoke machine pipe and the water heater pipe location are determined first, when the ceiling is installed, it will be cut according to some pipes, aluminum gusset plates, click to enter.

Related questions
10 answers2024-01-27

With the improvement of people's living standards, people's demand for bathroom space has gradually changed from a single grooming requirement to a comfortable and beautiful all-round experience. As a result, the integrated ceiling came into being and became the first choice of consumers. So how to choose in the face of so many integrated ceilings, and what kind of bathroom is most suitable? >>>More

8 answers2024-01-27

For the decoration of the kitchen, it is usually the reason why the ceiling is installed first, and then measured by the designer after the ceiling is installed, and then the cabinet is installed after the size is determined. >>>More

8 answers2024-01-27

Yes, some people in order to save the ceiling area, on the top of the cabinet that has been installed first, the wooden strips are used to fix the corners of the ceiling, but the formal practice is to first hang the ceiling and then make the cabinet, so that it will not step on the countertop, will not scratch the door panel.

11 answers2024-01-27

When you take the room, you can let the cabinets do the initial amount, help you drain the water and electricity, and then you first finish the kitchen bricklayer, and then find the cabinet maker to do a finer measurement to determine the specific size, as for the ceiling, it is better to install it first, in fact, the impact is not big, custom cabinets are about a month cycle, you can take advantage of this time to do a good job in the kitchen bricklayer decoration.

9 answers2024-01-27

It must be suspended first, and the cabinets must be installed after the wall tiles are pasted - this is the general procedure for decoration construction. Otherwise, it will not only affect the construction of the ceiling, but also may damage the cabinets, and there will be a lot of dust、、、 when the painter is about to finish, it is not too late to install the cabinets.