What are the steps to decorate a house? Flooring, suspended ceilings, doors, anmen, wall painting, k

Updated on Suspended ceilings 2024-01-28
6 answers
  1. Anonymous users2024-01-23

    Simple installation process: first design the bottom water circuit pay-off positioning Set door measurement cabinet measurement Hydropower positioning water and electricity heating transformation Water pressure test and electrical insulation test Bathroom waterproofing Do water shielding test Waterproof acceptance Waterproof floor plastering Kitchen and bathroom wall brushing Kitchen and bathroom pre-arranged bricks paste kitchen and bathroom wall tiles Wall top surface brush interface agent Wall plaster leveling (after kitchen wall tiles are pasted) Cabinet secondary measurement, confirm the drawings Paste cabinet bathroom floor tiles Wall scraping putty Wall polishing Kitchen and bathroom ceiling installation Wall top surface brush primer Wall top surface brush first coat top paint Wall repair Installation heating Sanitary ware installation Installation of set doors, cabinet installation, second topcoat, switch and socket installation, equipment, lamps and lanterns installation, hardware installation, curtain installation, waste land cleaning, completion acceptance.

  2. Anonymous users2024-01-22

    1: Handyman demolishes the wall and removes the slag.

    2: Hydropower transformation.

    3: Masonry powder repair, floor tile leveling, tiling.

    4: carpentry ceiling, cabinet, including doors and windows (such as clear water paint, carpentry first brush the primer on the panel) 5: painter furniture paint, wall paint.

    6: Switch socket, lamp installation.

    7: Hardware sanitary ware installation.

    8: Laminate flooring (wood flooring).

    9: Hygiene. 10: Furniture curtains.

  3. Anonymous users2024-01-21

    Hydropower wiring.

    Bricklayer: Sticking to the wall and floor tiles.

    Carpentry: door and window covers, various cabinets.

    Bricklaying; Wall putty sanding.

    Install the fixtures. Painter: Painting walls, various wood surfaces.

    Install the flooring. Install the light fixtures.

    Each decoration company is roughly like this, and there is little difference, which is much the same.

  4. Anonymous users2024-01-20

    1. Civil renovation (such as walling).

    2: Hydropower transformation.

    3. Mason (paving walls and floor tiles).

    4. Carpentry. After the panels enter the site, the wooden panels are first brushed with primer.

    5. Painter.

    6. Install lights, switches, sockets, and sanitary ware (let the painter repair the latex paint after completion) 7. Install wooden floors.

    8. Install curtains.

    9. Clean and prepare for check-in.

  5. Anonymous users2024-01-19

    First arrange the line, the line can be paved, and then the ceiling, the top can be hung to brush the wall, and then the carpenter enters, big wood, door covers, doors, cabinet installation, wood, and then the painter enters.

    After the paint is finished, you can install sanitary ware, switches, lights, etc.

  6. Anonymous users2024-01-18

    Cloth wires, wall scraping putty, brush the first paint, paving, install doors and windows, wall decoration, play all kinds of kitchen cabinets, install all kinds of sanitary ware, brush the second paint, install all kinds of lamps and appliances, cleaning, install air conditioning, place furniture, open windows to let out smell.

Related questions
5 answers2024-01-28

Step: Pre-design --2Main body demolition --3

Hydropower Renovation --4Carpentry --5Tiling --6 >>>More

7 answers2024-01-28

Many decoration whites do not have any understanding of the ceiling, in fact, this is very easy to understand, the ceiling is actually through a layer of false ceiling veneer, talking about the pipe and the top line in the house are hidden measures, so as to ensure the overall beauty of the space, after all, the pipe is leaking outside is indeed too ugly. >>>More

1 answers2024-01-28

The decoration of the new house should first open the trunking, take the water, electricity, heating, and then make up the trunking waterproofing, and then lay the wall and floor tiles, find the floor, and then dry the ceiling or gypsum line, interior doors, and then scrape the wall, wall paint, wallpaper, etc., and then install switch sockets, curtains, wooden floors, toilets, washstands, etc., electrical appliances, sofas, etc., and it will be successful.

2 answers2024-01-28

It's best not to, there should be no provision in the decoration that the door of the toilet cannot be aligned with the door of the room, but the decoration is according to the individual's own wishes. You can decorate as much as you like. It's because everyone thinks differently that there are all kinds of houses... >>>More

2 answers2024-01-28

Generally speaking, it depends on what kind of area, if it is an area that often needs to be cared for, it is recommended that you choose a stain-resistant color tile here, combined with the decoration renderings of your home and the decoration style.