What are the steps of the gypsum board ceiling construction process

Updated on Suspended ceilings 2024-01-27
4 answers
  1. Anonymous users2024-01-23

    Installation steps: 1. The keel ceiling hanger is fixed with expansion bolts and reinforced concrete slabs;

    2. 8 suspension bars and accessories fix 50 or 75 main keel; Middle distance 900mm;

    3. Fix 50 keels in turn;

    4. Or 12 thick paper gypsum board, fixed with self-tapping screws and keel;

    5. Full scraping of 2 thick surface layers of water-resistant putty;

    6. Paint finish.

  2. Anonymous users2024-01-22

    Ceiling decoration is a stage that must be experienced in the process of home decoration, the installation of ceilings is very important for interior decoration, and there are four common ceilings in the current home decoration industry, gypsum board ceilings, aluminum gusset ceilings, integrated ceilings, and soft ceilings. Among them, gypsum board ceilings are more concerned, so let's learn about them from the following. Construction process: Bullet roof elevation line - draw keel binning line - install the main keel boom - install the main keel - install the side keel - install the secondary keel - install gypsum board - paint - finish cleaning - sub-item - inspection batch acceptance.

    Construction technology 1Bullet roof level: According to the design elevation, the ceiling elevation line is played along the wall around, and along the elevation line of the roof, the keel binning position line is drawn on the wall.

    2.Install the main keel boom: after playing the ceiling elevation line and the dragon position line, determine the elevation of the lower end of the boom and install the boom.

    Straight installation is fixed to the structural ceiling with expansion bolts. The specifications of the boom meet the design requirements, and the spacing is less than 1200mm. 3.

    Installation of the main keel: the spacing of the main dragon is 900 1200mm. The main keel is connected with the boom with the matching dragon hanger.

    4.Install the secondary keel: the secondary keel spacing is 500mm 600mm, and the secondary pendant is connected with the main keel.

    5.Brush anti-rust paint: The light steel skeleton cover panel ceiling boom and fixed boom iron parts should be brushed with anti-rust paint before the cover panel.

    6.Installation of gypsum board: The way of fixing gypsum board and light steel skeleton adopts the self-tapping screw fixing method, and the installation is thick and reverse under the light steel skeleton that has been installed and experienced (that is, to do concealed acceptance work).

    The installation of the gypscale board is fixed with self-tapping screws, and the fixed spacing is 200mm on the edge of the board and 300mm in the board. After the self-tapping screws are fixed, the anti-rust paint is brushed. 7.

    Seam treatment: Paste paper tape caulking paste is used between the seams of the board for caulking treatment. The above content is the steps of the gypsum board ceiling construction process, I hope you can help you after understanding.

  3. Anonymous users2024-01-21

    4.°²500mm~600mm£¬²

  4. Anonymous users2024-01-20

    Construction process.

    Elevation line of the bullet roof - draw the keel binning line - install the main keel boom - install the main keel - install the side keel - install the secondary keel - install gypsum board - paint - finish cleaning - sub-item - inspection batch acceptance.

    Construction technology. 1.Bullet roof level: According to the design elevation, the ceiling elevation line is played along the wall around, and along the elevation line of the roof, the keel binning position line is drawn on the wall.

    2.Install the main keel boom: after playing the ceiling elevation line and the dragon position line, determine the elevation of the lower end of the boom and install the boom.

    Straight installation is fixed to the structural ceiling with expansion bolts. The specifications of the boom meet the design requirements, and the spacing is less than 1200mm.

    3.Installation of the main keel: the spacing of the main dragon is 900 1200mm. The main keel is connected with the boom with the matching dragon hanger.

    4.Install the secondary keel: the secondary keel spacing is 500mm 600mm, and the secondary pendant is connected with the main keel.

    5.Brush anti-rust paint: The light steel skeleton cover panel ceiling boom and fixed boom iron parts should be brushed with anti-rust paint before the cover panel.

    6.Installation of gypsum board: The way of fixing gypsum board and light steel skeleton adopts the self-tapping screw fixing method, and the installation is thick and reverse under the light steel skeleton that has been installed and experienced (that is, to do concealed acceptance work).

    The installation of the gypscale board is fixed with self-tapping screws, and the fixed spacing is 200mm on the edge of the board and 300mm in the board. After the self-tapping screws are fixed, the anti-rust paint is brushed.

    7.Seam treatment: Paste paper tape caulking paste is used between the seams of the board for caulking treatment.

Related questions
12 answers2024-01-27

1. Clean up the base layer.

2. The density of light steel keel frame or 3*4 wooden keel frame (for fire treatment) is not more than 600*600 >>>More

4 answers2024-01-27

Installation method of soft film ceiling.

Step 1: Install the keel. >>>More

7 answers2024-01-27

The installation of decorative gypsum board ceiling can be set up according to the material conditions of various places, such as shelving and flattening, screw fixing and adhesive bonding. (1) Shelving flat method: when using T-shaped aluminum alloy keel or light steel keel, the decorative gypsum board can be shelved in each grid frame composed of T-shaped keel, that is, to complete the ceiling construction. >>>More

3 answers2024-01-27

The elastic line is copied out of the horizontal point on each wall (column) corner in the room with a level meter (if the wall is longer, a few points should be copied in the middle), and the horizontal line is popped up (the horizontal line is generally 500 from the ground), from the horizontal line to the design height of the ceiling, the horizontal line is popped up along the wall (column) with the pink line, which is the lower skin line of the ceiling grille. At the same time, according to the ceiling plan, the position of the main keel is ejected on the concrete roof. The main keel should be divided from the center of the ceiling to both sides, the maximum spacing is 1000, and mark the fixed point of the boom, the fixed point spacing of the boom 900 1000. >>>More

1 answers2024-01-27

It mainly depends on the application environment and the type and material of the ceiling. Generally, it is a back-shaped ceiling and an L-shaped ceiling, and the original roof will be left in the middle to install the main light. Even if there is a whole cap, the place where the lamp is installed will be resealed with a wooden board as the backing of the gypsum board. >>>More