To decorate bathrooms and kitchens, do you install doors or tiles first?

Updated on Bathroom 2024-01-27
16 answers
  1. Anonymous users2024-01-23

    Generally speaking, it is to put the bricks first and then open the door, unless you have some other advanced needs

  2. Anonymous users2024-01-22

    There are two scenarios to consider.

    First: If it is a wooden door, it is necessary to paste the bricks first and then install the door cover and door. In this way, the edge is better and more beautiful.

    Second: is an aluminum alloy door or a plastic steel door, it is necessary to install the door first and then paste the brick, because the aluminum alloy and plastic steel door is a relatively simple door, it only has the door frame without the door sleeve, and the edge of the brick can not be closed, so it is necessary to install the door first and then paste the brick door edge to look good.

    If the door is installed first, the height of the floor tiles will be different, resulting in the gap under the door to be reserved too high. However, the wall tiles attached to the back can perfectly match and reinforce the door frame. If the wall tiles are pasted first, they will not fit well enough with the door frame installed later.

  3. Anonymous users2024-01-21

    There are two situations, 1. It is a wooden door, and it is necessary to paste the brick first and then install the door cover and door. In this way, the edge is better and more beautiful. 2. It is an aluminum alloy door or a plastic steel door, it is necessary to install the door first and then paste the brick, because the aluminum alloy and plastic steel door are relatively simple doors, it only has the door frame and no door sleeve, and the edge of the brick can not be closed, so it is necessary to install the door first and then paste the brick door edge to look good.

  4. Anonymous users2024-01-20

    Install the door frame first and then put the tiles, my kitchen and bathroom do this, the rest of the place is wooden flooring, first install the door, and finally lay the wooden floor.

  5. Anonymous users2024-01-19

    Of course, it is to be tiled first, and there is no objection to this!

  6. Anonymous users2024-01-18

    Paste the tile first and then install the door, which should be made of the door cover is wrapped in tiles, rather than using tiles to wrap the door cover.

  7. Anonymous users2024-01-17

    Generally, the door is installed first and then tiled, because the tiles on the side of the door need to be cut and then poured at a 45-degree angle.

  8. Anonymous users2024-01-16

    The tiles and sill stones are laid first, and then the door is installed.

  9. Anonymous users2024-01-15

    Of course, the bricks were laid first!

  10. Anonymous users2024-01-14

    Of course, when you install the kitchen and bathroom doors, the decoration of your home should be over.

  11. Anonymous users2024-01-13

    Install the door or door frame first.

  12. Anonymous users2024-01-12

    Paste the bricks first, lay the bricks first, and then install the door, and install the door after the bricks are paved, which will not affect the brick laying and do not delay the construction period, so the general construction party will take this approach.

    If the door is laid first, it will affect the process of brick laying, and the process of brick laying will also damage the door.

  13. Anonymous users2024-01-11

    First the door cover, then the tile, and then the door frame.

  14. Anonymous users2024-01-10

    In the process of renovating the bathroom and kitchen, in general, we will first lay the bricks and then install the door. This order is based on several reasons. First of all, the installation of the door needs to be carried out under the condition of a flat wall, and the paving of bricks can make the wall more flat, which is conducive to the installation of the door.

    Secondly, if the door is installed first, it may affect the paving of the bricks and may even cause damage to the door. Finally, the installation of the door is usually carried out in the final stage of the renovation to prevent unnecessary damage to the door during the renovation process.

    The specific quotation for house decoration can be calculated here, just enter the area + city, calculate the decoration quotation in 3 seconds, know the real price in advance, and easily grasp the decoration company: [Click here to calculate the decoration quotation for free].

    In the local market, the price of bricks usually ranges from 30-300 yuan per square meter, depending on the material, brand and specifications of the bricks. The price of the door ranges from 500 to 5,000 yuan per door, depending on the material, brand and design of the door. These prices are for reference only, and the specific decoration cost also needs to be determined according to the actual situation and personal needs.

    When decorating, it is recommended that you first find a professional renovation company or worker, who will provide you with a reasonable renovation plan and budget according to your needs and budget. At the same time, it is also recommended that when choosing bricks and doors, you should consider not only the price, but also their quality and durability to ensure the effectiveness and longevity of the decoration. During the renovation process, it is also necessary to pay attention to protecting the facilities that have been installed to avoid damage to them during the decoration process.

    Finally, we recommend our "Tuba Rabbit", Tuba Rabbit has 110,000 decoration companies and suppliers in hand, and the direct sales of building materials are affordable. Tuba Rabbit is selected for decoration, and Tuba Rabbit can accompany the signing of the contract for free, "decorate first and then make payment", reducing the worries of the owners. For more decoration information, welcome to visit:

    Click to enter, professional customer service free consultation good company].

    Kunming - [Kunming Decoration Strategy Guide].

    Suzhou - [Suzhou Decoration Strategy Guide].

    Hefei - [Hefei Decoration Strategy Guide].

    Fuzhou - [Fuzhou Decoration Strategy Guide].

    Beijing - [Beijing Decoration Strategy Guide].

    Dalian - [Dalian Decoration Strategy Book].

    Hangzhou - [Hangzhou Decoration Strategy Guide].

    Shanghai - [Shanghai Decoration Strategy Guide].

    Tianjin——[Tianjin Decoration Strategy Guide].

  15. Anonymous users2024-01-09

    Generally, bricks will be pasted first, because the bathroom has a slope paving, which is convenient for water to flow to the floor drain.

    It will be easier to install when the door is installed in the later stage. In addition, there will be some differences according to the type of door used, such as wooden doors, which should be tiled first and then installed with door covers.

    with the door. In this way, the edge is better and more beautiful.

    2. It is an aluminum alloy door or a plastic steel door, it is necessary to install the door first and then paste the brick, because the aluminum alloy and plastic steel door are relatively simple doors, it only has the door frame and no door sleeve, and the edge of the brick can not be closed, so it is necessary to install the door first and then paste the brick door edge to look good.

  16. Anonymous users2024-01-08

    I'm a home improvement guy.

    Generally, the ground is paved first.

    If there is no time to install the door for the time being.

    You can ask the brick laying master to lay the wall tiles in the bathroom and kitchen to a position where there is only one brick away from the door, and then make the door.

    The bricklayer master finishes up.

    Relatively easy to do.

Related questions
4 answers2024-01-27

If the smoke pipe is buried in the ceiling, the smoke pipe should be embedded before the ceiling, and the ceiling and the cabinet do not conflict, but the most comfortable order is: embedded smoke pipe - ceiling - cabinet - smoke machine stove! It's okay to hang the ceiling first, and it's very convenient to dismantle the ceiling!

8 answers2024-01-27

Yes, some people in order to save the ceiling area, on the top of the cabinet that has been installed first, the wooden strips are used to fix the corners of the ceiling, but the formal practice is to first hang the ceiling and then make the cabinet, so that it will not step on the countertop, will not scratch the door panel.

2 answers2024-01-27

Generally, kitchen cabinet companies will recommend that you choose kitchen appliances of what size, and then install electrical appliances after the kitchen cabinet installation is completed (if possible, the electrical appliances are installed on the same day, the cabinet is installed in the morning, and the electrical appliances are installed in the afternoon before the cabinet installer is gone), and they can solve the problem together if they find the best!!

1 answers2024-01-27

Decoration is generally done in the order of first doing the top and then the bottom, if your range hood is installed lower than the cabinet, then you should install the cabinet first.

13 answers2024-01-27

To renovate a kitchen, you need to make cabinets first, and then install a range hood according to the height of the stove and pot. The hood must be directly fixed on the wall, and the formal installation method of the range hood is to use expansion bolts to horizontally fix the range hood on the concrete or brick wall wall, not directly on the non-load-bearing wall wall, let alone on the cabinet.