How many hours after the kitchen and bathroom are waterproof, put the water off for a few days

Updated on Kitchen 2024-01-28
5 answers
  1. Anonymous users2024-01-23

    After doing waterproofing, the time of the closed water test is 48-72 hours, and you can do the closed water test after the waterproof layer is completely dry, generally about 24 hours can be completely dry (2 days ago, it is recommended to do the waterproof for about two days in 48 hours (the time is not standardized, the standard is to see if the waterproof is dry), 24 hours after the closed water test, go downstairs to see if there is a water leak.

    In order to have a good waterproof effect, the waterproof coating must be painted three times, the drying period of the one-component environmentally friendly polyurethane coating is about 3 4 days, if the waterproof material is painted in a rainy day, the effect of the waterproof coating will not be very good.

    Before laying floor tiles, it is necessary to do a good job of waterproofing engineering; After the tile is laid, it is necessary to ensure that the brick surface has a drainage slope (, the slope is towards the floor drain, which is conducive to wastewater discharge.

  2. Anonymous users2024-01-22

    After the bathroom is waterproofed, wait until the waterproof layer is completely dry before you can do the closed water test. Generally, it can be completely dried in about 24 hours, and the time of closed water test is 48-72 hours.

  3. Anonymous users2024-01-21

    After waterproofing for about two days (the time is not standardized, the standard is to see whether the waterproof is dry), the closed water test is more than 24 hours to 48 hours, and 48 hours is recommended.

  4. Anonymous users2024-01-20

    24 hours after the closed water test, go downstairs to see if there is any leakage.

  5. Anonymous users2024-01-19

    Wait for it to dry and leave the water in place for 24 hours.

Related questions
2 answers2024-01-28

There is no charge for any public toilet anywhere in the UK. >>>More

2 answers2024-01-28

Buy 2 barrels of Black Henkel (20kg a barrel, a barrel can brush 8 10 square meters), sell about 110 on Taobao, do it yourself, it will be 220 yuan, half a day. The store will tell you the specific operation.

4 answers2024-01-28

This depends on how big your leakage area is, as well as the leakage situation, the maintenance master waterproofing agent (no brick smashing) hopes to serve you again.

3 answers2024-01-28

The price of waterproofing in the bathroom has a lot to do with the type of waterproof material used, the brand, the local price, the price, etc. >>>More

5 answers2024-01-28

Do waterproofing time.

After the hydropower renovation is completed, waterproofing will be done immediately. It should be noted that waterproofing should be done as much as possible at the base layer of the structure. >>>More